THE
GOVERNMENT
-------
|
SOCIALIST
REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
|
No: 43/NQ-CP
|
Hanoi, June 06,
2014
|
RESOLUTION
ON
SOME PRIMARY TASKS IN REFORM OF ADMINISTRATIVE PROCEDURES FOR FORMULATION AND
EXECUTION OF INVESTMENT PROJECTS USING LAND TO IMPROVE BUSINESS ENVIRONMENT
THE GOVERNMENT
Pursuant to the Law on Government organization
dated December 25, 2001;
Pursuant to the Decree No. 01/NQ-CP dated
January 07, 2013 of the Government on the managerial solutions for the
implementation of the Plan for the economic development and the budget estimate
in 2013;
Pursuant to the Decree No. 01/NQ-CP dated
January 02, 2014 of the Government on the managerial solutions for the
implementation of the Plan for the social-economic development and the budget
estimate in 2014;
At the request of the Minister of Justice
RESOLVE
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Article 2. Some primary
tasks in the reform of administrative procedures for formulation and execution
of investment projects using land include:
1. The regulations on the administrative procedures
for the formulation and execution of investment projects using land are simplified
as follows:
The components of the procedures for the
appointment of the investors using land are standardized and regulated in 3
forms: land use right auction (hereinafter referred to as land auction),
bidding to choose the investors running the investment projects using land,
land allocation and land lease without bidding or auctions
- With regard to the land auction: the
components of the procedures for the land auction of which the appointment of
the investors eligible to run the investment projects is integrated with the
land auction procedure, are specifically regulated.
- With regard to the bidding to choose the
investors running the investment projects using land:
The conditions of the bidding to choose the
investors running the investment projects using land include: The projects in
the list of the bidding to choose the investors which are approved and
published by the competent authorities; Projects in an area of which the
detailed planning on a scale of 1:500 has been approved; Projects in an area of
which compensation plan has been approved; Projects of which the unit price of
land levy and land rents has been approved.
The components of the procedures for the bidding to
choose the investors running the investment projects using land are
specifically regulated.
The result of these administrative procedures is
the written approval for the appointment of the investors. A written approval
for the appointment of the investor must include: The name of the project, name
of the investor/owner, investment method, investment objectives, location for
construction, investment scale, land use area, land use boundaries, planning
and architectural targets such as: land coefficient, building density…; total
investment in the project, unit price of land levy/ land rents; time and
implement progress (divided according to stages), capital resources, management
and operation methods, investment incentives (if any).
- With regard to land allocation and land
lease in order to run the investments projects without bidding and auctions:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+Such result of the administrative procedures must
include: The name of the project, the name of the investor, investment method,
investment objectives, location for construction, project scale, land use area,
scope, boundaries, land scale, population in the urban planning area (if any);
requirements of planning(1- With regard to the construction projects of
construction groups: The land use targets for the houses, commercial services;
social infrastructure projects, trees, traffic; targets for the use of urban
planning land for the whole planning area; requirements for the organization of
the architectural area, landscape and environment; requirements for the targets
and major constructions of the urban technical infrastructure which serve as a
basis for the owners to outline the tasks and detail planning plan. 2- With
regard to construction projects of individual constructions: The urban planning
land use targets in terms of numbers of stories, land use coefficient, building
density of the land; requirements for construction architecture and
environment, requirements for the targets for urban technical infrastructure
and other requirements that the owners can use to formulate the investment
projects of the constructions), total investment in the projects, time and
implementation progress (divided according to stages); capital resources;
management and operation methods, investment incentives and investment support.
With regard to procedures for the investment
registration or assessment, issuance of the investment certificates:
- The procedures for the investment
registration or assessment, issuance of the investment certificates for the
project of investment using land that invest in the fields in which investment
is subject to conditions are annulled.
- With regard to the investment projects
using land involved in the fields in which investment is subject to conditions:
The procedures for the assessment, issuance of the
investment certificates in case of the land auction, bidding to choose the
investors running the investment projects using land and the investors running
the investment projects using land within their rights are replaced by the
simple procedures for the investment registration which include only the
information about the investment projects.
The contents of the procedures for the investment
registration and assessment, the issuance of the investment certificates are
integrated with the contents of the procedures for the approval for the
investment policies into one comprehensive procedure in case of land allocation
and land lease to run the investment projects without bidding and auctions.
Such result of the administrative procedures is the investment registration
certificate.
With regard to the procedures related to the
construction planning.
- The investors are not required to implement the
procedures for the issuance of the planning permits; the contents of the
planning permits must be included in the result of the procedures for the
approval for the investment policies.
- According to the result of the procedures for the
approval for the investment policies, the investors shall outline and approve
the specific planning tasks in order to set up the planning projects.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
dd) The single-window system is applied to the implementation
of the assessment procedures for the need to use land, the conditions for the
land allocation and land lease; procedures for the land allocation and land
lease in case of the investment projects obliged for implementing the above
assessment procedures.
The procedures for the bidding for the land
valuation consultancy in order to provide the consultancy services in a
specific period of time are considered and regulated to shorten the time to
select the consultancy services and determine specific land prices.
g) The continuity mechanism between the governing
authorities in charge of natural resources and environment and governing
authorities in charge of tax is considered and applied to the handling of the
administrative procedures for land. The governing authorities of natural
resources and environment are the agency in charge of receipt and provision of
the result for the investors.
h) The issuance of the construction permits are not
required in case of projects in an area of which the detailed planning on a
scale of 1:500 has been approved.
i) With regard to the investment projects of the
constructions that related to the confirmation, and inspection of final
assessment of the constructions before they are put into operation of different
governing authorities, the governing authorities in charge of construction
shall take charge and receive the requests of the investors and establish
interdisciplinary task forces to confirm and assess the projects for the
investors. It is not allowed to establish more than one inspectorate. The times
of inspection depends on the scale and technical nature of the constructions.
However, the special Class constructions are inspected at most 4 times, the
Class I constructions are inspected at most 3 times and the others are at most
2 times except for the constructions confronting problems of quality during the
execution or other cases that are requested by the investors.
k) The requirements, production and business
conditions are considered and reviewed towards the reduction in the
requirements of the practice certificates before the registration of enterprise
establishment, certificates of eligibility or permits of operation. Providing
that the procedures for the issuance of the operation permits or certificates
of eligibility for operation must be implemented, the detailed and consistent
policies, standards, regulations and social-economic norms must be considered
and promulgated to serve as a basis for the implementation.
a) During the time the regulations related to the
laws and ordinances to perform the tasked prescribed in Clause 1 of this
Article have not been amended, replaced and annulled completely, the
administrative procedures for the formulation and execution of the investment
projects using land shall be completed and standardized based on the Appendix 1
attached to this Resolution, ensuring these principles:
- The single-window system is utilized so that each
investor shall come to one authority, summit one application once and receive
several results from different authorities.
- Several administrative procedures can be
implemented concurrently to reduce the implementation time of the investors.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
a) After the regulations related to the laws and
ordinances to perform the tasked prescribed in Clause 1 of this Article have
been amended, replaced and annulled completely, the administrative procedures
for the formulation and execution of the investment projects using land shall
be completed and standardized based on the Appendix II attached to this
Resolution.
a) Based on the administrative procedures for the
formulation and execution of the investment projects using land promulgated
together with the Appendix I and Appendix II, the administrative procedures for
the investment projects shall be completed, standardized and specified in order
to be published with regard to the peculiar projects of such majors and fields.
3. The administrative procedures for the investment
projects must be implemented publicly as follows:
a) The administrative procedures must be seriously
published, which serves as a basis for the implementation of the administrative
procedures and elimination of the corruption and misconduct. The administrative
procedures must be published on the National database of the administrative
procedures and publicized in the head offices in the authorities or units
directly dealing with the administrative procedures.
b) The application of the information technology to
the receipt and handling of administrative procedures shall be enhanced. The
information about the results of the administrative procedures of the
investment projects, especially the reasons for the overdue implementation
shall be published on the websites of the Ministries, ministerial agencies,
Governmental agencies, the People’s Committees of the provinces in order to be
monitored by the individuals and organizations.
4. The inspections of the implementation of the
administrative procedures in the authorities at all level shall be enhanced;
the officials and civil servants who encumber or fail to discharge their duties
on the implementation of the regulation on the administrative procedures, the
organizations and agencies that do not seriously publish the administrative
procedures or tardily amend the regulations on the administrative procedures
for the implementation of the investment projects which are unnecessary,
unreasonable, illegal and ineffective under the direction of the competent
authorities or competent persons shall be strictly penalized in time.
Article 3. Implementation
1. 1. With regard to the legislative documents
within the promulgation authority of the Government, Prime Minister, Ministries
and Heads of ministerial-level agencies (prescribed in the attached Appendix
III):
a) The Ministries and ministerial-level agencies
shall propose amendments, replacement and annulment of the regulations on
administrative procedure according to the approved tasked which is prescribed
in Clause 2 this Decree to promulgate or request the Government and Prime
Minister to consider promulgating before October 15, 2014. Amendments to
multiple documents should be included in one document according to simplified
procedures.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. 2. Ministry of Planning and Investment shall
consider including the solutions to the reform of the administrative procedures
which is adopted by the Government in the Law on Investment (amended) while the
Law project is established and completed in order to be submitted to the
National Assembly. With regard to the administrative procedures prescribed in
the law and ordinance needing amending according to the approved tasks in this
Decree but not included in the Formulation of law and ordinance programme, the
Minister of Justice, authorized by the Prime Minister, on behalf of the
Government is assigned to report the proposal of the Government for the
permission to add the law and ordinance project to implement the solutions to
the reform of the administrative procedures which is adopted by the Government
to the formulation of law and ordinance programme in 2015 to the Standing
Committee of the National Assembly before December 31, 2014
3. During the implementation, the Ministry of
Planning and Investment, Ministry of Finance, Ministry of Natural Resources and
Environment, Ministry of Construction and other relevant Ministries and
regulatory agencies shall proactively detect, amend, replace or annul the
relevant regulations in time within their authority or send a written request
to the Ministry of Justice and Government Office for the laws, ordinances,
Decrees of the Government, decision of the Prime Minister regulating the
administrative procedures that need amending, replacing or annulling in order
to perform the tasks in the reform of the administrative procedures approved by
the Government in the Article 2 in this Resolution.
4. 4. The People’s Committees of the provinces and
centrally-run cities (hereinafter referred to as provinces) shall perform the
tasks mentioned in the Article 2 this Decree, immediately amend, replace or
annul the relevant regulations in the documents within their authority
according to the legislative documents issued by the central agencies and ensure
the implementation of those documents when they become effective.
5. 5. The ministries, ministerial-level agencies,
government agencies, People's Committees of provinces shall perform the tasks
related to the implementation of the administrative procedures for the
formulation and execution of the investment projects using land which are
approved by the Government in this Decree according to their ambit of
competence. The ministries, ministerial-level agencies shall perform the tasks
prescribed in Point c Clause 2 of Article 2 in this Decree in order to publish
and implement nationwide.
6. 6. The Ministry of Justice shall take charge and
cooperate with other Ministries, regulatory agencies and local authorities in
examining and supervising the implementation; report the difficulties that
arises during the performance of the tasks approved by the Government in this
Decree to the Prime Minister for consideration; send a partial report to the
Government by the end of 2016 on the implementation result of such performance
of the assigned tasks in this Resolution.
7. 7. The Consultancy Council of the administrative
procedure reform shall take charge and cooperate with the Ministries,
regulatory authorities and local authorities in evaluating the implementation
of this Resolution.
Article 4. The ministries,
ministerial-level agencies, government agencies, People's Committees of
provinces preferably allocate the budget to ensure the completion of the
assigned tasks in this Resolution. The Ministry of Finance shall balance and
ensure sufficient budget for the performance of the tasks prescribed in this
Resolution.
In addition to the regular funding resources, the
ministries, ministerial-level agencies, government agencies, the People's
Committees of provinces are allowed to mobilize other financial resources to
facilitate the performance of the tasks in this Decree.
Article 5. This Decree
takes effect as of the signing date.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
ON BEHALF OF
THE GOVERNMENT
PRIME MINISTER
Nguyen Tan Dung
APPENDIX I
ADMINISTRATIVE PROCEDURES FOR FORMULATION AND
EXECUTION OF INVESTMENT PROJECTS USING LAND
(In
case the relevant laws and ordinances have not been amended, replaced
and annulled completely)
(Issued together
with the Resolution No. 43/NQ-CP dated June 06, 2014 of the Government)
The administrative procedures for the formulation
and execution of the standardized investment projects using land are
implemented as follows:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
No
Names of the
administrative procedures
Regulated
objects
Agencies in
charge
Processing
duration
Note
1
Land auctions:
The investment projects using the land prescribed
in the List of land auctions which are approved by the competent authorities
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
30 working days
Result
- Approval for the successful bid
- Certificates of the land right
2
Investment Registration
The investment projects using land which is up
for auction
The governing authorities in charge of investment
05 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3
Collection of opinions about fundamental design
With regard to the investment projects of the
constructions within the urban scale which is approved by The governing
authorities, the investors must collect the opinions about the fundamental
design of The governing authorities before the projects are approved. With
regard to other projects, the investors shall decide whether to collect
opinions about the fundamental design if necessary.
Regulatory authorities
Group C: 10 working days
Group B: 15 working days
Group A: 20 working days
4
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The investment projects for the constructions as
prescribed in the Appendix 3 attached to the Decree No. 46/2012/ND-CP
Fire departments
15 working days
These administrative procedures may be
implemented simultaneously
5
Commitment to environmental protection/ Approval
for the report on the environmental impact assessment
- The projects whose environmental impact
assessment must be assessed and approved
The projects within the authority over the
investment policies of the National Assembly and the Prime Minister
+ The projects using land of the wildlife
sanctuaries, national parks, cultural-historic sites, world heritage sites,
biosphere reserves, ranked scenic beauties
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- The projects that are required to fulfill the
commitment to environment protection: The production, business and service
establishments whose scale is as households, run the projects of the
industries and fields that are likely to cause environmental pollution.
The authorities of Natural resources and
Environment
- Commitment to environment protection : 05
working days
- Approval for the report on the environmental
impact assessment: 45 working days.
6
Design assessment
The investment projects for the constructions
including:
a) Apartment buildings of Class III or above;
separate houses, each of which has at least 7 floors.
b) Public works of Class III or above;
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
d) Traffic constructions: Bridges, tunnels, roads
of Class III or above which are funded from the State budget and of Class II
or above which are funded from other capital; railways, airports, terminals,
floating docks, inland ports, system of cable transport for people system,
regardless of Classes;
dd) Agricultural constructions: reservoirs, dams,
drains, channels, closed water pipes, hydraulic tunnels, dikes, embankments,
pumping stations and other Irrigational works regardless of Classes;
e) Infrastructural constructions: Infrastructural
constructions of Class III or above which are funded from the State budget
and of Class II or above funded from other capital; hazardous solid waste
treatment constructions regardless of Classes.
The regulatory authorities in charge of
construction.
- Constructions of Class I or above: 40 working
days
- Other constructions: 30 working days
7
Announcement to begin construction
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The owners
8
Inspection of final assessment of the constructions
before they are put into operation
The investment projects for the constructions
including:
a) Apartment buildings of Class III or above;
separate houses, each of which has at least 7 floors.
b) Public works of Class III or above;
c) Industrial constructions: Transmission lines,
hydroelectric plants, thermal power plants, smelters, alumina manufacturing
plants, cement plants of Class III or above; petrochemical plants, gas
processing plants, storage buildings, gas, oil, liquefied petroleum pipelines,
manufacturing plants and warehouses of hazardous chemicals, and industrial
explosives regardless of Classes;
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
dd) Agricultural constructions: reservoirs, dams,
drains, channels, closed water pipes, hydraulic tunnels, dikes, embankments,
pumping stations and other Irrigational works regardless of Classes;
e) Infrastructural constructions: Infrastructural
constructions of Class III or above which are funded from the State budget
and of Class II or above funded from other capital; hazardous solid waste
treatment constructions regardless of Classes.
The governing bodies in charge of construction
- Class III and IV: 15 working days
- Special Class, Class I and II: 30 working days
The governing authorities in charge of
construction shall take charge and receive the request applications of the
investors and establish the interdisciplinary task forces to conduct
inspections and inform each investor once for all.
9
Assessment and confirmation of the implementation
of the projects and environmental protective measures to facilitate the
operation of the projects
The investment projects that are required to file
reports on the environmental impact assessment.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- The competent authorities in charge of
handling: The authorities of Natural resources and Environment
20 working days
10
Issuance of the permits for the operation,
certificates of eligibility
Projects that invest in the fields in which
investment is subject to conditions
The Regulatory authorities.
Depending on the form and scale of each project
The processing duration must be time-saving for
the clients and suit the implementation ability of the authorities in charge
of administrative procedures.
2. With regard to the bidding to choose the
investors to run the investment projects using land.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Names of the administrative
procedures
Regulated
objects
Agencies in
charge
Processing
duration
Note
1
Bidding to choose the investors to run the
investment projects using land.
The investment projects prescribed in the List of
bidding to choose the investors to run the investment projects using land
which are approved by the competent authorities
The appointed authorities in charge of bidding
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2
Investment Registration
The investment projects which are put up for
bidding in order to choose the investors to run the investment projects using
land
The governing authorities in charge of investment
05 working days
3
Announcement of land revocation
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The authorities of Natural resources and
Environment
According to the regulations of the Law on Land
4
Collection of opinions about fundamental design
With regard to the investment projects of the
constructions within the urban scale which is approved by the governing
authorities, the investors must collect the opinions about the fundamental
design of the governing authorities before the projects are approved. With
regard to other projects, the investors shall decide whether to collect
opinions about the fundamental design if necessary.
Regulatory authorities
Group C: 10 working days
Group B: 15 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
5
Assessment of the fire safety design
The investment projects for the constructions as
prescribed in the Appendix III attached to the Decree No. 46/2012/ND-CP
Fire departments
15 working days
These administrative procedures may be
implemented simultaneously
6
Information/ agreement on the water supply and
drainage, electricity supply
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The regulatory authorities.
10 working days
7
Design assessment
The investment projects for the constructions
including:
a) Apartment buildings of Class III or above;
separate houses, each of which has at least 7 floors.
b) Public works of Class III or above;
c) Industrial constructions: Transmission lines,
hydroelectric plants, thermal power plants, smelters, alumina manufacturing
plants, cement plants of Class III or above; petrochemical plants, gas
processing plants, storage buildings, gas, oil, liquefied petroleum
pipelines, manufacturing plants and warehouses of hazardous chemicals, and
industrial explosives regardless of Classes;
d) Traffic constructions: Bridges, tunnels, roads
of Class III or above which are funded from the state budget and of Class II
or above which are funded from other capital; railways, airports, terminals,
floating docks, inland ports, system of cable transport for people system,
regardless of Classes;
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
e) Infrastructural constructions: Infrastructural
constructions of Class III or above which are funded from the State budget
and of Class II or above funded from other capital; hazardous solid waste
treatment constructions regardless of Classes.
The regulatory authorities in charge of
construction.
- Constructions of Class I or above: 40
working days
- Other constructions: 30 working days
These administrative procedures may be
implemented simultaneously
8
Commitment to environmental protection/ Approval
for the report on the environmental impact assessment
- The projects whose environmental impact assessment
must be assessed and approved
The projects within the authority over the
investment policies of the National Assembly and the Prime Minister
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ The projects that have negative effects on the
environmental and social factors.
- The projects that are required to fulfill the
commitment to environment protection: The production, business and sevice
establishments whose scale is as households, run the projects of the
industries and fields that are likely to cause environmental pollution.
Authorities of Natural resources and Environment
- Commitment: 05 working days
- Assessment and approval: 45 working days.
9
Decision on land allocation, land lease and
transfer of land use purposes.
The investment projects using land
The authorities of Natural resources and
Environment
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
10
Announcement and implementation of the
compensation plan for the premises clearance
The projects using land which is revoked by the
government
The organizations in charge of compensation,
premises clearance, the People's Committees of districts and communes
90 working days
Including:
- Announcement and receipt of the suggestions for
the plan: 20 working days
- Approval for the plan: 05 working days.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Provision of the compensation: 40 working days
from the announcement of the approved plan
- Land allocation: 20 working days from the
complete provision of the compensation.
11
Land lease contract singing/ fulfillment of
financial obligations to the State
The investment projects using land
Authorities of Natural resources and Environment;
Tax authorities
10 working days
12
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The investment projects using land
The authorities of Natural resources and
Environment
5 working days
13
Issuance of the certificates of the land rights
The investment projects using land
The authorities of Natural resources and
Environment
07 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
14
Announcement to begin construction
The investment projects for the constructions
The owners
15
Inspection of final assessment of the
constructions before they are put into operation
The investment projects for the constructions including:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b) Public works of Class III or above;
c) Industrial constructions: Transmission lines,
hydroelectric plants, thermal power plants, smelters, alumina manufacturing
plants, cement plants of Class III or above; petrochemical plants, gas
processing plants, storage buildings, gas, oil, liquefied petroleum
pipelines, manufacturing plants and warehouses of hazardous chemicals, and
industrial explosives regardless of Classes;
d) Traffic constructions: Bridges, tunnels, roads
of Class III or above which are funded from the state budget and of Class II
or above which are funded from other capital; railways, airports, terminals,
floating docks, inland ports, system of cable transport for people system,
regardless of Classes;
dd) Agricultural constructions: reservoirs, dams,
drains, channels, closed water pipes, hydraulic tunnels, dikes, embankments,
pumping stations and other Irrigational works regardless of Classes;
e) Infrastructural constructions: Infrastructural
constructions of Class III or above which are funded from the State budget
and of Class II or above funded from other capital; hazardous solid waste
treatment constructions regardless of Classes.
The governing authorities in charge of
construction
- Class III and IV constructions: 15 working days
- Special Class, Class I and II constructions: 30
working days
The governing authorities in charge of construction
shall take charge and receive the request applications of the investors and
establish the interdisciplinary task forces to conduct inspections and inform
each investor once for all.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Assessment and confirmation of the implementation
of the projects and environmental protective measures to facilitate the
operation of the projects
The investment projects that are required to file
reports on the environmental impact assessment.
- The authorities in charge of receiving
requests: The governing bodies in charge of construction
- The competent authorities in charge of
handling: Authorities of Natural resources and Environment
20 working days
17
Issuance of the permits for the operation,
certificates of eligibility
Projects that invest in the fields in which
investment is subject to conditions
The Regulatory authorities.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The processing duration must be time-saving for
the clients and suit the implementation ability of the authorities in charge
of administrative procedures.
3. With regard to the land allocation, land lease
without bidding or auctions
No
Names of the
administrative procedures
Regulated
objects
Agencies in
charge
Processing
duration
Note
1.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(Enclosed with
details of the administrative procedures)
The land allocation and land lease without
bidding and auctions as prescribed in the Law on Land and other cases other
than the investment projects executed by the investors on their land.
Provincial departments of Planning and
Investment
30-60 working days
Result
- The written approvals for the investment
policies (their contents are prescribed in the investment permits, using the attached
form)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2.
Formulation, assessment and approval for the
detail planning/ total premises planning
The investment projects of the urban
construction, including:
a) The projects whose boundaries or some targets
for the use of urban planning land need adjusting in order to execute the
investment projects to build construction groups
or individual constructions in the areas whose detail planning has been
approved.
b) The investment projects to build the construction
groups in the urban areas having no detail planning
c) The investment projects to build the
individual constructions in the urban areas having no detail planning or
urban design, except for housing.
The governing bodies in charge of planning, the
People's Committee of provinces
30-40 working days (Assessment: 25, Approval: 15)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Collection of opinions about fundamental design
With regard to the investment projects of the constructions
within the urban scale which is approved by the governing authorities, the
investors must collect the opinions about the fundamental design of the
governing authorities before the projects are approved. With regard to other
projects, the investors shall decide whether to collect opinions about the
fundamental design if necessary.
The regulatory authorities
Group C: 10 working days
Group B: 15 working days
Group A: 20 working days
These administrative procedures may be
implemented simultaneously
4.
Information/ agreement on the water supply and
drainage, electricity supply
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The regulatory authorities.
10 working days
5.
Assessment of the fire safety design
The investment projects for the constructions as
prescribed in the Appendix 3 of the Decree No. 46/2012/ND-CP
Fire departments
15 working days
6.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The housing development projects and new urban
area project investment projects
The Provincial departments of Construction
30 or 65 working days depending on the type of
each project
7.
Commitment to environmental protection/ Approval
for the report on the environmental impact assessment
- The projects whose environmental impact
assessment must be assessed and approved
The projects within the authority over the
investment policies of the National Assembly and the Prime Minister
+ The projects using land of the wildlife
sanctuaries, national parks, cultural-historic sites, world heritage sites,
biosphere reserves, ranked scenic beauties
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- The projects that are required to fulfill the
commitment to environment protection: The production, business and sevice establishments
whose scale is as households, run the projects of the industries and fields
that are likely to cause environmental pollution.
The authorities of Natural resources and
Environment
- Commitment to environment protection : 05
working days
- Approval for the report on the environmental
impact assessment: 45 working days.
These administrative procedures may be
implemented simultaneously
8.
Announcement of land revocation
The investment projects using land which is
revoked by the government
The authorities of Natural resources and
Environment
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
9.
Decision on land allocation, land lease and
transfer of land use purposes.
The investment projects using land except for the
investment projects using land subject to the legal rights of the investors
and conformable with the approved planning
The authorities of Natural resources and
Environment
30 working days
10.
Data collection, formulation, approval and announcement
of the compensation plan for the premises clearance, provision of
compensation, receipt of premises
The investment projects using land which is
revoked by the government
The organizations in charge of compensation,
premises clearance, the People's Committees of districts and communes
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Including:
- Announcement and receipt of the suggestions for
the plan: 20 working days
- Approval for the plan: 05 working days.
- Announcement of the approved plan: at most 03
working days from the receipt of the plan
- Provision of the compensation: 40 working days
from the announcement of the approved plan
- Land allocation: 20 working days from the
complete provision of the compensation.
11.
Hire of the units to file the applications for
the valuation of the land levy and land rents.
The investment projects using land except for the
investment projects using land subject to the legal rights of the investors
and conformable with the approved planning
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
10 working days
12.
Assessment of the valuation applications,
determination of the unit price of the land levy, land rents
The investment projects using land except for the
investment projects using land subject to the legal rights of the investors
and conformable with the approved planning
The Provincial departments of Finance and
other relevant regulatory authorities
10 working days
13.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The investment projects using land except for the
investment projects using land subject to the legal rights of the investors
and conformable with the approved planning
The People's committees of provinces
10 working days
14.
Land lease contract singing/ fulfillment of
financial obligations to the State
The investment projects using land except for the
investment projects using land subject to the legal rights of the investors
and conformable with the approved planning
The provincial departments of Natural resources
and Environment; Tax authorities
10 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
15.
Receipt of land on the map and on site
The investment projects using land except for the
investment projects using land subject to the legal rights of the investors
and conformable with the approved planning
The provincial departments of Natural resources
and Environment
5 working days
16.
Issuance of the certificates of the land rights
The investment projects using land except for the
investment projects using land subject to the legal rights of the investors
and conformable with the approved planning
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
07 working days
17.
Design assessment
The investment projects for the constructions
including:
a) Apartment buildings of Class III or above;
separate houses, each of which has at least 7 floors.
b) Public works of Class III or above;
c) Industrial constructions: Transmission lines,
hydroelectric plants, thermal power plants, smelters, alumina manufacturing
plants, cement plants of Class III or above; petrochemical plants, gas
processing plants, storage buildings, gas, oil, liquefied petroleum
pipelines, manufacturing plants and warehouses of hazardous chemicals, and
industrial explosives regardless of Classes;
d) Traffic constructions: Bridges, tunnels, roads
of Class III or above which are funded from the state budget and of Class II
or above which are funded from other capital; railways, airports, terminals,
floating docks, inland ports, system of cable transport for people system,
regardless of Classes;
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
e) Infrastructural constructions: Infrastructural
constructions of Class III or above which are funded from the State budget
and of Class II or above funded from other capital; hazardous solid waste
treatment constructions regardless of Classes.
The regulatory authorities in charge of
construction.
- Constructions of Class I or above: 40
working days
- Other constructions: 30 working days
These administrative procedures for land may be
implemented simultaneously
18.
Announcement to begin construction
The investment projects for the constructions
The owners
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
19.
Inspection of final assessment of the
constructions before they are put into operation
The investment projects for the constructions
including:
a) Apartment buildings of Class III or above;
separate houses, each of which has at least 7 floors.
b) Public works of Class III or above;
c) Industrial constructions: Transmission lines,
hydroelectric plants, thermal power plants, smelters, alumina manufacturing
plants, cement plants of Class III or above; petrochemical plants, gas
processing plants, storage buildings, gas, oil, liquefied petroleum
pipelines, manufacturing plants and warehouses of hazardous chemicals, and
industrial explosives regardless of Classes;
d) Traffic constructions: Bridges, tunnels, roads
of Class III or above which are funded from the state budget and of Class II
or above which are funded from other capital; railways, airports, terminals,
floating docks, inland ports, system of cable transport for people system,
regardless of Classes;
dd) Agricultural constructions: reservoirs, dams,
drains, channels, closed water pipes, hydraulic tunnels, dikes, embankments,
pumping stations and other Irrigational works regardless of Classes;
e) Infrastructural constructions: Infrastructural
constructions of Class III or above which are funded from the State budget
and Class II or above funded from other capital; hazardous solid waste
treatment constructions regardless of Classes.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Class III and IV constructions: 15 working days
- Special Class, Class I and II constructions: 30
working days
The governing authorities in charge of
construction shall take charge and receive the request applications of the
investors and establish the interdisciplinary task forces to conduct
inspections and inform each investor once for all.
20.
Assessment and confirmation of the implementation
of the projects and environmental protective measures to facilitate the
operation of the projects
The investment projects whose environmental impact
assessment has been reported.
- The authorities in charge of receiving
requests: The governing bodies in charge of construction
- The competent authorities in charge of
handling: Authorities of Natural resources and Environment
20 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Issuance of the permits for the operation,
certificates of eligibility
Projects that invest in the fields in which
investment is subject to conditions
The Regulatory authorities.
Depending on the form and scale of each project
The processing duration must be time-saving for
the clients and suit the implementation ability of the authorities in charge
of administrative procedures.
CONTENTS OF
PROCEDURES
APPROVAL FOR THE
INVESTMENT POLICIES
(With regard
to land allocation and lease in order to run the investments projects without
bidding and auctions)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- The investors file and send the valid
applications to the Provincial Departments of Planning and Investment based on
the investment demands, public information about land planning, construction
planning and specialist planning
- The provincial departments of Planning and
Investment check, receive and provide the appointment notes of the return of
the applications
- Within 05 days from the receipt of the
applications, the provincial Departments of Planning and Investment shall
examine and send written notifications that require the amendments to the
applications (if any)
- After receiving the complete valid applications,
the provincial Departments of Planning and Investment shall directly verify and
send the written requests for the cooperation in verifying the applications to
the relevant Ministries, Departments, regulatory authorities and the People’s
Committees of districts to verify the contents related to the ambit of
competence of specific authorities:
+ The provincial Departments of Planning and
Investment shall verify the information which is provided by the investors to
issue the Investment certificates under the regulations of the Law on investment
and guiding documents on the Law on investment.
+ The Provincial departments of Constructions (and
the provincial Departments of Planning if any) shall verify the information
about the construction locations, construction boundaries, conformability to
the construction planning, regulations and standards of the construction
planning, requirements to the owners during the formulation of planning,
investment projects, and requirements for the infrastructure connection under
the regulations of the law.
+ The provincial Departments of Natural Resources
and Environment shall verify the information about the conformability to the
planning, land use plan, need to use land, conditions for land allocation and
land lease as prescribed in the Law on Land and guiding documents on the
implementation of the Law on Land; the requirements of the environment as
prescribed in the Law on Environment protection and guiding documents on the
implementation of the Law on Environment protection; the compliant with laws on
land and environment of the investors.
+The management boards of the Economic Zones,
Industrial Zones, Processing and Exporting Zones shall verify the information
about locations, planning, areas and investment projects within their
competence.
+ The provincial Departments, regulatory
authorities or Ministries shall verify the information related to their
specialities under the regulations of laws (if any)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- In case of any the investment project whose
location and boundaries have not been specified, the provincial Departments of
Planning and Investment shall hold an interdisciplinary meeting to reach an
agreement with the provincial departments, regulatory authorities and the
People’s Committees of districts on the locations, boundaries to formulate the
investment project after 15 days from the delivery of the written request for
the cooperation in verifying the application.
- The provincial departments, regulatory
authorities and the People’s Committees of districts shall file a written
verification under the regulations and send it to the provincial Departments of
Planning and Investment in order to send a report to the People’s Committees of
provinces after 7 days form the meeting or 20 days from the delivery of the
written request of the provincial Departments of Planning and Investment. In
case the cooperating authorities do not reply within the prescribed time, they
shall be penalized and the competent authorities shall consider and decide the
contents of the projects within their functions and tasks; the presiding
authority is the cooperating authority approving and taking the next steps.
- After 7 days from the receipt of the written
verifications of the provincial departments, regulatory authorities and the
People’s Committees of districts, the provincial Departments of Planning and Investment
shall compile and submit them to the People’s Committees or send a report to
the Prime Minister for the approval for the investment policies.
- The People’s Committees of districts shall
approve the investment policies or send a report to the Prime Minister for the
approval for the investment policies after 10 days from the receipt of the
report of the provincial Departments of Planning and Investment.
- The investors shall receive the result of the
procedures for the approval of the investment policies at the provincial
Departments of Planning and Investment and the Certificates of Business
registration, tax codes and seals in case of foreign investors requesting the
formulation of the investment projects associating with the establishment of the
enterprises.
In case the investors request of the investment
projects associating with the establishment of the enterprises, according to
the approval for the investment policies and requesting applications of the
investors, the provincial Departments of Planning and Investment shall issue
the Business registration certificates, the Provincial Department of Taxation
shall provide the tax codes and the Police departments shall provide the seals
within 5 days from the date the results are available.
2. Components of an application:
- The written request for the approval for the
investment policies
- Legal entity application
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ In case of an investment project associating with
the establishment of an economic organization, the investors must attach:
(1) A business registration application in
proportion to each type of enterprise as prescribed in the laws of enterprises
and relevant law provisions.
(2) A joint-venture contract in case of the
establishment of the joint-venture economic organization of the Vietnamese and
foreign investors.
- The plan for the investment project including:
the necessary of the investment, aims, scale, location, predicted boundaries,
architectural planning targets, total investment capital, capital resources;
project process; need to use land; technology and environment solutions.
- A report on the investors’ financial capacity
(which the investor compiles and takes responsibility for) and the documents
showing the equity capital under the regulations.
- The diagram of the location, map of the current
conditions of the land, the certificate of the land right (if any).
* The number of the applications: 10 (including the
ones for the presiding authority to send to the relevant provincial
Departments, regulatory authorities and authorities of districts).
3. Implementation Methods
Directly or by post.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- The projects within the authority of the People’s
Committees of districts: at most 39 working days, in case of associating with
the establishment of the enterprises: at most 44 working days.
- The projects within the authority of the Prime
Minister: at most 60 working days, in case of associating with the
establishment of the enterprises: at most 65 working days.
5. Regulated objects
Individuals and organizations.
6. Agencies in charge
- The competent authorities in charge of giving
decisions: the Prime Minister or the People’s Committees of provinces.
- The authorities in chare of implementation: the
provincial Departments of Planning and Investment (where the projects are
expected to be launched).
- Cooperating authorities: Ministries,
ministerial-level agencies; provincial Departments, regulatory authorities and
the People's Committee of districts.
7. Fees
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
8. Result
- The written approvals for the investment policies
(using form).
- Investment certificates (if any).
- Certificates of Business registration (if any).
- Tax codes (if any).
- Seals (if any).
9. Requirements:
- The investors must have business registration
conformable with the activities of the investment projects.
- The investors’ investment capital for the
investment projects are higher than 20% of the total investment of the projects
using land whose area is less than 20 ha, and higher than 15% of the total
investment of the projects using land whose area is more than 20 ha.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The written request form for the approval for
the investment policies
Owner’s name
SOCIALIST
REPUBLIC OF VIET NAM
Independence - Freedom – Happiness
No...............
.................,.............................
REQUEST
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
To: the Prime
Minister or the People’s Committee of province.
Investor/Owner (name of the investor/owner)..............................request
the Prime Minister / the People’s Committee of ....................... to
consider approving the policies of the project (name of the
project)...........................including these following main contents:
1. Name of the project..........................
2. Name of the investor/owner:
3. Investment method:
4. Investment aims:
5. Location for construction:
6. Project scale:
7. Land use area:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
9. Land use coefficent:
10. Building density:
11. Total investment of the project:
12. Implementation time and progress (divided
according to stages)
13. Capital resources;
14. Project management and operation plan:
15. Suggestions of owner:
16. Conclusion:
Investor/Owner (name of the investor/owner)..............................request
the Prime Minister / the People’s Committee of .......................for
consideration and approval./.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Name of the
investor/owner:
(Sign, write
name, title and seal if any)
The written approval form for the investment
policies (using form).
THE PRIME
MINISTER/ THE PEOPLE'S COMMITTEE OF..................
SOCIALIST
REPUBLIC OF VIET NAM
Independence - Freedom – Happiness
No...............
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
DECISION
On the approval
for the investment policies of the project.............
THE PRIME
MINISTER/ THE PEOPLE’S COMMITTEE OF..................
Pursuant to the Law on investment;
Pursuant to the Laws on……………………………… (having
related regulations);
Pursuant to the Decree No………………………………………………..;
In consideration of the Request for the approval
for the investment policies of the project (name of the
project).............No…………of (name of the owner)…………………..and attached
application;
In consideration of the Request
No…………………dated………………..of (name of the assessment agency or the People’s
Committee of the district)……………………and the suggestions of the relevant
authorities (names the authorities that offer opinion and the number of the
written suggestions.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Article 1: On the approval for the investment
policies of the project (name of the project)..........................
1. Name of the project..........................
2. Name of the investor/owner:
3. Investment method:
4. Investment aims:
5. Location for construction:
6. Project scale:
7. Land use area:
8. Scope, boundaries, scale of the land, population
of the area in the urban planning (if any):
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- With regard to the investment projects to build
construction groups: The land use targets for the houses, commercial services;
social infrastructure projects, trees, traffic; targets for the use of urban
planning land for the whole planning area; requirements for the organization of
the architectural area, landscape and environment; requirements for the targets
and major constructions of the urban technical infrastructure which serve as a
basis for the owners to outline the tasks and detail planning plan;
- With regard to the investment projects to build
individual constructions: The urban planning land use targets, land use
coefficient, building density of the land; requirements for construction
architecture and environment, requirements for the targets for urban technical infrastructure
and other requirements that the owners can use to formulate the investment
projects of the constructions.
10. Total investment of the project:
11. Implementation time and progress (divided
according to stages)
12. Capital resources;
13. Project management and operation plan:
14. Investment incentives.
Article 2. On the implementation…………….
Article 3. This Decision takes effect as of the
signing date.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
THE PRIME
MINISTER
THE
REPRESENTATIVE OF PEOPLE’S COMMITTEE OF…………….
(Sign, write
name, title and seal)
APPENDIX II
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(In case of
the relevant laws and ordinances have been completely amended, replaced and
annulled)
( Issued
together with the Resolution No. 43/NQ-CP dated June 06, 2014 of the
Government)
The administrative procedures for the formulation
and execution of the investment projects using land are standardized as
follows:
1. With regard to land auctions:
No.
Names of the
administrative procedures
Agencies in
charge
Processing
duration
Note
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Land auction
The appointed autioneer
30 working days
Result: Approval for the successful bid,
Certificates of the land use right
2
Investment Registration
The governing authorities in charge of
construction
05 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Collection of opinion about design basis
The regulatory authorities
Group C:10 working days
Group B:15 working days
Group A: 20 working days
These administrative procedures may be
implemented simultaneously
4
Assessment of the fire safety design
The fire Departments
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
5
Commitment to environmental protection/ Approval
for the report on the environmental impact assessment
The authorities of Natural Resources and
Environment
- Commitment to environmental protection:
05 working days
- Approval for the report on the environmental
impact assessment
6
Design assessment
The regulatory authorities in charge of
construction
- Constructions of Class I or above: 40
working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
7
Announcement to begin construction
The owners
8
Inspection of final assessment of the
constructions before they are put into operation
The governing authorities in charge of
construction
- Class III and IV constructions: 15
working days.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The interdisciplinary task force shall be
established to receive the applications, review and confirm the investors
once and for all.
9
Assessment and confirmation of the implementation
of the projects and environmental protective measures to facilitate the
operation of the project
- The governing authorities in charge of
construction shall receive the requests
- The governing authorities in charge of
environment shall handle them
20 working days
10
Issuance of the permits for the operation,
certificates of eligibility
The regulatory authorities
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. With regard to the bidding to choose the
investors to run the investment projects using land:
No.
Names of the
administrative procedures
Agencies in
charge
Processing
duration
Note
1.
Bidding to choose the investors to run the investment
projects using land
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
According to the regulations in Article 12, Law
on Bidding
Result: The written approval for the appointed
investor; The contract for the investment in the project.
2.
Investment Registration
The governing authorities in charge of investment
05 working days
3.
Announcement of land revocation
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
According to the regulations of the Law on Land
4.
Collection of opinion about design basis
The regulatory authorities
Group C:10 working days
Group B:15 working days
Group A: 20 working days
These administrative procedures may be
implemented simultaneously
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Information/ agreement on the water supply and
drainage, electricity supply
The regulatory bodies
10 working days
6.
Assessment of the fire safety design
The fire Departments
15 working days
7.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The regulatory bodies in charge of construction
- Constructions of Class I or above: 40
working days
- Other constructions: 30 working days
These administrative procedures may be
implemented simultaneously
8.
Commitment to environmental protection/ Approval
for the report on the environmental impact assessment
The people’s Committee of districts, authorities
of Natural Resources and Environment
- Commitment: 05 working days
- Approval: 45 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Decision on land allocation, land lease and
transfer of land use purposes
Authorities of Natural Resources and Environment
30 working days
10.
Announcement and implementation of the
compensation plan for the premises clearance
The organizations in charge of compensation,
premises clearance, the People's Committees of districts and communes
90 working days
11.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The provincial Departments of Natural Resources
and Environment; Tax authorities
10 working days
12.
Receipt of land on map and on site
The provincial Departments of Natural Resources
and Environment
05 working days
13.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The provincial Departments of Natural Resources
and Environment
07 working days
14.
Announcement to begin construction
The owners
15.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The governing authorities in charge of
construction
- Class III and IV constructions: 15
working days.
- Special Class, Class I and II constructions: 30
working days
The interdisciplinary task force shall be
established to receive the applications, check and confirm
16.
Assessment and confirmation of the implementation
of the projects and environmental protective measures to facilitate the
operation of the projects
The authorities of Natural Resources and
Environment
20 working days
17.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The regulatory authorities
Depending on the form and scale of each project
3. With regard to the land allocation, land lease without
bidding or auctions:
No.
Names of the
administrative procedures
Agencies in
charge
Processing
duration
Note
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Approval for the investment policies
The provincial Departments of Planning and
Investment
30-60 working days
Result: Investment registration certificates
2.
Formulation, assessment and approval for the
detail planning/ total premises planning
The governing bodies in charge of planning, the
People's Committee of provinces
30-40 working days (Assessment: 25, Approval: 15)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Collection of opinions about fundamental design
Regulatory authorities
Group C:10 working days
Group B:15 working days
Group A: 20 working days
These administrative procedures may be
implemented simultaneously
4.
Information/ agreement on the water supply and
drainage, electricity supply
Regulatory bodies
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
5.
Assessment of the fire safety design
The fire Departments
15 working days
6.
Approval for the investment in the housing
development projects/ approval for the investment in the new urban area
project assessment
The Provincial departments of Construction
30 or 65 working days depending on the type of
each project
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
7.
Commitment to environmental protection/ Approval
for the report on the environmental impact assessment
The authorities of Natural Resources and
Environment
- Commitment: 05 working days
- Approval: 45 working days
These administrative procedures may be
implemented simultaneously
8.
Announcement of land revocation
The People’s Committees of districts
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
9.
Decision on land allocation, land lease and
transfer of land use purposes
The authorities of Natural Resources and Environment
30 working days
10.
Data collection, formulation, approval and
announcement of the compensation plan for the premises clearance, provision
of compensation, receipt of premises
The organizations in charge of compensation, premises
clearance
90 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
11.
Hire of the units to file the applications for
the valuation of the land levy and land rents
The valuation units
10 working days
12.
Assessment of the valuation applications, determination
of the unit price of the land levy, land rents
The provincial departments of Finance and
other relevant regulatory authorities
10 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
13.
Approval for the unit price of the land levy and
land rents
The People’s Committees of districts
10 working days
14.
Land lease contract singing/ fulfillment of
financial obligations to the State
The provincial Departments of Natural Resources
and Environment; Tax authorities
10 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
15.
Receipt of land on map and on site
The provincial Departments of Natural Resources
and Environment
5 working days
16.
Issuance of the certificates of the land rights
The provincial Departments of Natural Resources
and Environment
07 working days
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
17.
Design assessment
The regulatory bodies in charge of construction
- Constructions of Class I or above: 40
working days
- Other constructions: 30 working days
Design assessment and the administrative
procedures for land shall be implemented simultaneously
18.
Announcement to begin construction
The owners
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
19.
Inspection of final assessment of the
construction before it is put into operation
The governing authorities in charge of construction
- Class III and IV constructions: 15
working days.
- Special Class, Class I and II constructions: 30
working days
The interdisciplinary task force shall be
established to receive the applications, check and confirm the investors once
20.
Assessment and confirmation of the implementation
of the projects and environmental protective measures to facilitate the
operation of the project
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
20 working days
21.
Issuance of the permits for the operation,
certificates of eligibility
Regulatory authorities
Depending on the form and scale of each project
APPENDIX III
LIST OF LEGISLATIVE DOCUMENTS REQUIRING AMENDING,
REPLACING
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. Law on Investment;
2. Law on Urban planning
3. Law on Construction
II. LIST OF LEGISLATIVE DOCUMENTS WITHIN
PROMULGATION AUTHORITY OF THE GOVERNMENT, PRIME MINISTER, MINISTRIES, HEADS OF
MINISTERAL-LEVEL AGENCIES
1. In the field of Planning and Investment
- Decree No. 108/2006/Decree-CP dated September 22,
2006 of the Government detailing and providing instructions on some Articles of
the Law on Investment
- Decree No. 113/2009/Decree-CP dated December 15,
2009 of the Government on the investment supervision and evaluation.
- Circular No. 03/2009/TT- BKH dated April 16, 2009
of the Ministry of Planning and Investment on the instructions on the
appointment of the investors investing in the projects using land.
2. In the field of Construction
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Decree No. 37/2010/ND-CP dated April 07, 2010 of
the Government on the formulation, assessment, approval and administration of
the urban planning.
- Decree No. 64/2012/ND-CP dated September 04, 2012
of the Government on the issuance of the construction permits.
- Decree No. 15/2013/ND-CP dated February 06, 2013
of the Government on the construction quality control.
- Circular No. 07/2008/TT- BKH dated April 07, 2008
of the Ministry of construction providing instructions on the formulation,
assessment, approval and administration of the urban planning.
- Circular No. 16/2010/TT-BXD dated September 01, 2010
of the Ministry of Construction detailing and providing instructions on the
implementation of some Articles of the Decree No. 71/2010/ND-CP dated June 23,
2010 of the Government detailing and providing instructions on the
implementation of the Law on Housing.
- {0Circular No.
10/2010/TT-BXD dated August 11, 2010 of the Ministry of Construction regulating
the application of each type of urban planning.
Circular No. 23/2012/TT-BTC dated February 16, 2012
of the Ministry of Finance providing instructions on the collection, payment
and administration of the use of the fees for the issuance of the planning
permits.
- Circular No. 10/2012/TT-BXD dated December 20,
2012 of the Ministry of Construction detailing some Articles of the Decree No.
64/2012/ND-CP dated September 04, 2012 of the Government on the issuance of the
construction permits.
3. In the field of Natural resources and
Environment: - Decree No. 29/2011/ND-CP dated April 18, 2011 of the Government
regulating strategic environment assessment, environmental impact assessment
and commitment to environment protection.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Circular No. 26/2011/TT-BTNMT dated July 18, 2011
of the Ministry of Natural Resources and Environment detailing some Articles of
the Decree No. 29/2011/ND-CP dated April 18, 2011 of the Government imposing
regulations on the strategic environment assessment, environmental impact
assessment and commitment to environment protection.
The processing duration is the
period of time from the submission of the applications of the investors to the
receipt of the result of the administrative procedures. The progressing time is
specified as the maximum period of time. With regard to the land auctions and
bidding to choose the investors executing the investment projects using land,
the processing time is specified from the deadline for the auction applications
or bid packages to the receipt of the administrative procedures.