MINISTRY OF LABOR - INVALIDS AND SOCIAL AFFAIRS OF
VIETNAM
--------
|
THE SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
|
No. 17/2021/TT-BLDTBXH
|
Hanoi, November 15, 2021
|
CIRCULAR
PROMULGATING PROCEDURE FOR
INSPECTION OF TECHNICAL SAFETY OF INDUSTRIAL GAS CYLINDERS UNDER MANAGEMENT OF
THE MINISTRY OF LABOR - INVALIDS AND SOCIAL AFFAIRS
Pursuant
to the Law on Occupational Safety and Health dated June 25, 2015;
Pursuant
to the Government’s Decree No. 14/2017/ND-CP dated February 17, 2017
defining the functions, tasks, powers and organizational structure of the
Ministry of Labor - Invalids and Social Affairs;
Pursuant
to the Government’s Decree No. 44/2016/ND-CP dated May 15, 2016 elaborating
on several Articles of the Law on Occupational Safety and Health on technical
inspection of occupational safety, occupational safety and health training and
workplace environment monitoring;
Pursuant
to the Government’s Decree No. 140/2018/ND-CP dated October 08, 2018 on
amendments to Decrees related to business conditions and administrative
procedures under the management of the Ministry of Labor - Invalids and Social
Affairs;
At the
request of the Director General of the Department of Work Safety;
The
Minister of Labor - Invalids and Social Affairs hereby promulgate a Circular on
procedure for inspection of technical safety of industrial gas cylinders under
management of the Ministry of Labor - Invalids and Social Affairs.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Promulgated
together with this Circular is the procedure for inspection of technical safety
of industrial gas cylinders under management of the Ministry of Labor -
Invalids and Social Affairs, code: QTKD: 06-2021/BLDTBXH.
Article 2. Effect
1. This
Circular comes into force from January 01, 2022.
2.
Inspection procedure No. QTKD: 06-2016/BLDTBXH Procedure for inspection of
technical safety of industrial gas cylinders promulgated together with the
Circular No. 54/2016/TT-BLDTBXH dated December 28, 2016 of the Ministry of
Labor - Invalids and Social Affairs shall cease to have effect from the
effective date of this Circular.
Article 3. Implementation
1.
Ministries, ministerial agencies, Governmental agencies, People’s Committees of
provinces and central-affiliated cities, organizations and individuals
concerned are responsible for the implementation of this Circular.
2.
Difficulties that arise during the implementation of this Circular should be
reported to the Ministry of Labor - Invalids and Social Affairs for
instructions and resolution./.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
PROCEDURE FOR INSPECTION OF
TECHNICAL SAFETY OF INDUSTRIAL GAS CYLINDERS UNDER MANAGEMENT OF THE MINISTRY
OF LABOR - INVALIDS AND SOCIAL AFFAIRS
CODE QTKD: 06-2016/BLDTBXH
(Promulgated with the Circular No. 17/2021/TT-BLDTBXH dated
November 15, 2021 of the Minister of Labor - Invalids and Social Affairs)
Article 1. Scope
This
technical safety inspection procedure shall be used for first, periodic and
unscheduled inspections of industrial gas cylinders with a working pressure of more than 0.7
bar (hereinafter referred to as “gas cylinders”) under state management of
the Ministry of Labor - Invalids and Social Affairs as prescribed in Appendix
Ib of the Government’s Decree No. 44/2016/ND-CP dated May 15, 2016 elaborating
on several Articles of the Law on Occupational Safety and Health on technical
inspection of occupational safety, occupational safety and health training and
workplace environment monitoring.
This
inspection procedure shall not be used for inspection of liquefied petroleum
gas (LPG) cylinders.
Article 2. Regulated entities
1.
Organizations carrying out technical inspections of occupational safety
(hereinafter referred to as “inspecting organization”).
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
3.
Organizations and individuals managing, using and owning industrial gas
cylinders (hereinafter referred to as “establishments”).
4.
Regulatory bodies, relevant organizations and individuals.
Article 3. Normative references
1.
National technical regulation on safe work of steam boiler and pressure vessel
QCVN:01-2008/BLDTBXH promulgated together with the Decision No.
64/2008/QD-BLDTBXH dated November 27, 2008 of the Ministry of Labor - Invalids
and Social Affairs (hereinafter referred to as “QCVN:01-2008/BLDTBXH”).
2. TCVN
6292:2013 Gas cylinders - Refillable welded steel cylinders issued
together with Decision No. 1475/QD-BKHCN dated June 12, 2013 of the Ministry of
Science and Technology (hereinafter referred to as “TCVN 6292:2013”).
3. TCVN
6294:2007 Gas cylinders - Welded carbon -steel gas cylinders issued -
Periodic inspection and testing issued together with Decision No.
3213/QD-BKHCN dated December 31, 2007 of the Ministry of Science and Technology
(hereinafter referred to as “TCVN 6294:2007”).
4. TCVN
6295:1997 Gas cylinders - Seamless gas cylinders - Safety and performance
criteria (of water capacities between 0.5 l to 150 l, regardless of any
pressure) issued together with Decision No. 2123/QD-BKHCN dated April 05, 2018
of the Minister of Science and Technology (hereinafter referred to as “TCVN
6295:1997”).
5. TCVN
6871:2007 Gas cylinders - Transportable cylinders for dissolved acetylene -
Periodic inspection and maintenance issued together with Decision No.
3213/QD-BKHCN dated December 31, 2007 of the Ministry of Science and Technology
(hereinafter referred to as “TCVN 6871:2007”).
6. TCVN
6156:1996 Pressure vessels - Safety engineering requirements of erection, use,
repair - Testing method issued together with Decision No. 1596/QD-TDC dated
July 26, 1996 of the Ministry of Science and Technology (hereinafter referred
to as “TCVN 6156:1996”).
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Article 4. Terms and definitions
For the
purposes of this inspection procedure, the following terms and definitions
apply:
1.
“industrial gas cylinder” means a cylinder which is used to contain and
transport gases, liquefied gas or dissolved gas (industrial gas) at a pressure
above atmospheric pressure and with a water capacity of up to 150 liters,
manufactured and labeled in accordance with the provisions of TCVN 6292:2013
and TCVN 6295:1997.
2. “first
safety inspection” means the evaluation of technical safety of an industrial
gas cylinder according to national technical regulations and technical safety
standards after its manufacturing and before its first use.
3.
“periodic safety inspection” means the evaluation of technical safety of
equipment according to national technical regulations and technical safety
standards after expiration of the last safety inspection result.
4.
“unscheduled safety inspection” means the evaluation of technical safety of
equipment according to national technical regulations and technical safety
standards after such equipment is repaired, replaced or processed affecting
technical safety of the cylinder or at the request of the establishment or a
competent authority.
Article 5. Inspection equipment and instruments
Inspection
equipment and instruments shall be inspected and calibrated in accordance with
regulations. Inspection equipment and instruments includes the following:
1.
Non-destructive thickness gauge.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
3.
Equipment for cylinder valve installation and removal.
4. Hydraulic
testing equipment.
5.
Cylinder leak tester.
6.
Volumetric expansion tester.
7.
Internal cylinder cleaning equipment.
8.
Equipment for in-cylinder examination by endoscopic method.
9. Vacuum
equipment.
10.
Electronic scale.
11.
Cylinder stamping equipment.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Article 6. Conditions for inspection
The
inspection of industrial gas cylinders must not be carried out unless the
following conditions are met:
1. The
cylinders are at the ready for inspection.
Gas
cylinders fully filled with gas before being imported into Vietnam must undergo
a first safety inspection according to the steps specified in clause 1 and
clause 2 Article 8 of this inspection procedure (excluding the steps specified
in clauses 3 through 8 Article 8 of this inspection procedure). The inspection
carried out by following all steps prescribed in Article 8 of this inspection
procedure shall be only applied to cylinders before being re-filled with gas
for subsequent use or cylinders due for inspection prescribed in Article 9 of
this inspection procedure.
2.
Documents of the cylinders are adequate.
3. The
inspection is not affected by environment or weather.
4.
Requirements concerning occupational safety and health are met.
Article 7. Preparation for inspection
Before
carrying out an inspection, it is required to make the following preparations:
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
a)
Preparing documents of the cylinders.
b)
Determining the cylinders to be inspected:
-
Regarding first safety inspection: Randomly select 5% of the batch of cylinders
to be inspected (the selected cylinders must be representative of the
sub-batches of cylinders). If any of the inspected cylinders is found failed,
100% of the cylinders in the batch must be inspected (according to point 4.2
TCVN 6156:1996).
-
Regarding periodic or unscheduled inspection: inspect 100% of the cylinders.
c)
Prepare a delivery record and make preparations in respect of human resources
and vehicles for transport of cylinders to the place of inspection.
d)
Preliminary inspection and instructions:
-
Immediately reject any cylinder which is not owned by the establishment or the
inspection of which is not requested by the authorized establishment;
- Reject
cylinders which are not listed or on which specifications are unavailable or
unclear, cylinders with defects exceeding the rejection limits such as: bulge,
dent, intersecting cut or gouge, crack, fire damage, arc or torch burns;
- Proceed
to release and treat the residual gases in the cylinders, making sure the
cylinders are free of pressure and residual gases;
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
dd) For
cylinders that have been filled with storage gas, when the periodic inspection
is due, such cylinders must be inspected at a rate of 5%.
- If the
inspected cylinders are passed, the remaining cylinders may be stored/used for
no more than one year;
- If any
of the inspected cylinders is failed, 100% of the remaining cylinders must be
inspected. The period of gas release for inspection of 100% of the cylinders
must not exceed one month.
e) Making
preparations in respect of human resources, supplies and equipment to serve the
inspection; appoint personnel to participate in and witness the inspection.
2.
Prepare suitable and adequate facilities for inspection.
3.
Develop safety measures and reach an agreement thereon with the establishment
before inspection. Provide adequate personal protective equipment to ensure
safety during the inspection.
Article 8. Inspection steps
Upon
conducting a technical safety inspection of gas cylinders, the inspector shall
follow the inspection steps in turn. The next inspection step is taken only
when the result of the previous step is passed. Inspection steps consist of:
1. Step
1: Examining documents, profiles or information of the cylinders
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
a) Upon
first safety inspection:
- Profile
of the cylinder batch and technical documents of the manufacturer (forms are
provided under QCVN 01-2008/BLDTBXH). The following documents should be
considered:
+
Indicators concerning manufacturing metals, welding metals;
+
Calculation of strength of pressure retaining components;
+
Structural drawings showing all main dimensions;
+
Guidelines on operation, maintenance and repair (if any);
+
Certificate of conformity issued by the designated organization as prescribed
in the case where the competent authority has promulgated national technical
regulations applicable to the inspected cylinders.
- Factory
acceptance record of the cylinder batch:
+
Certificate of the manufacturer, standards applied;
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
+
Certificate of manufacturing metals;
+ Record
and sheet of the strength and leak test results for the batch of cylinders;
+ Report
on examination of mechanical properties of welds;
+ Record
of the volumetric expansion test results;
+ Record
of the explosion test results;
+ Record
of the thickness and weld test results (if any).
b) Upon
periodic safety inspection:
-
Previous profile of the cylinder batch, inspection record and certificate of
inspection result or information and documents about the cylinders.
-
Documents on the use, operation and maintenance; inspection or examination
record (if any).
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
-
Documents on the use, operation and maintenance; inspection or examination
record (if any).
-
Documents on repair, post-repair acceptance record documenting the replacement
of pressure retaining components.
The
document and profile inspection result is passed if the documents and profiles
are adequate and comply with the regulations set out in point 2.4 QCVN:
01/2008/BLDTBXH. If failed, the establishment shall take remedial actions.
2. Step
2: External technical inspection
a) Check
the technical specifications stamped on the handle or neck of each cylinder,
compare them with the technical data on the cylinder on the list of cylinders
to be inspected. Reject cylinders not included in the list of cylinders to be
inspected and cylinders on which specifications are missing or blurred.
b) Check
the condition of the surface, welds, base, and handles (if any).
c) When
there is any suspicion during the visual inspection, additional tests or
examination measures must be applied such as: ultrasonic testing of thickness
or welds (if any) or other non-destructive testing measures.
d)
Evaluation: A cylinder is passed if its components remain normal, there is not
any unusual sign and specifications on the cylinder are consistent with those
on documents. Reject cylinders according to point 4.8 of TCVN 6156:1996,
Appendix C of TCVN 6294:2007 and Appendix C of TCVN 6871:2007.
3. Step
3: Internal technical inspection
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
-
Cylinders containing inert gas, non-toxic and non-flammable gases may be placed
in direct release position.
-
Cylinders containing toxic and flammable gases must be treated using
specialized equipment. The recovered gases may be used or treated safely and
must not be released directly into the environment.
b) Remove
valves from the cylinder head, prevent impact that can cause deformation or
damage to the cylinder’s valve or neck thread.
c)
Examine the tightness of the valves and safety parts (if any); reject failed
valves.
d) Clean
the inside of the cylinders (For acetylene cylinders containing porous mass,
the cleaning step is not required but the quality of the porous mass must be
checked according to the manufacturer's instructions or TCVN 6871:2007).
dd) Check
the inside of the cylinders with an endoscope to evaluate the metal
surface and welds (not applicable to soluble acetylene cylinders). In case of
any suspicion, request the establishment to adopt other appropriate measures.
e)
Evaluation: A cylinder is passed if its inside remains normal and there is not
any unusual sign. Reject cylinders according to point 4.8 of TCVN 6156:1996.
4. Step
4: Technical inspection of pressure resistance (strength test)
Strength
test shall not be performed on cylinders containing porous mass.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Table 1: Strength test pressure, test media and test
holding time
Type of cylinder
Test medium
Test pressure
(bar)
Holding time
(minute)
Normal
welded cylinder
Water
1.5
maximum working pressure
≥ 0,5
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Air or
inert gas
1.5
maximum working pressure
≥ 0,5
Seamless
cylinder
Water
1.5 maximum
working pressure
≥ 2
b)
Temperature of the test medium must be less than 50°C and must not fall below
the ambient temperature by more than 5°C.
c) The
pressure shall be increased or decreased slowly so as not to cause sudden
expansion, thereby affecting the cylinder’s strength.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
- Before
performing test with gas, the strength must be calculated according to actual
measurements of the cylinder
- Safety
measures in case of test with gas:
+ The gas
supply valve and sample pressure gauge on the gas inlet line must be placed
away from the cylinder location;
+ A
prohibition sign “No unauthorized entry to the test area” must be erected;
+ A safe
gas supply must be ensured.
Evaluation:
A cylinder is passed if the pressure does not decrease when maintained at the
test pressure, there is no leakage from the cylinder body or welds or there is
no deformation in excess of the prescribed limits.
dd) For
welded cylinders: carry out evaluation according to point 9.1 of TCVN
6292:2013.
e) For
seamless cylinders: carry out evaluation according to according to point C.4.3
of TCVN 6295:1997.
5. Step
5: Volumetric expansion test
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
a) Water
jacket method: Enclose the water-filled cylinder in a jacket that is also
filled with water. The total and any permanent volumetric expansion of the
cylinder are measured as to the amount of water displaced by the expansion of
the cylinder when under pressure and after the pressure is released (carry out
evaluation according to C.5.2.1 of TCVN 6295:1997).
b)
Non-water jacket method: Measure the amount of water passed into the cylinder
as it is pressurized to test pressure and measure the amount of water expelled
from the cylinder to reduce the pressure to atmospheric pressure. First measure
the amount of water while increasing the water pressure in the cylinder to
determine the total expansion of the cylinder at test pressure, then measure
the amount of water expelled from the cylinder, subtract that amount of water
from the total expansion to determine the permanent volumetric expansion (carry
out evaluation according to C.5.2.2 of TCVN 6295:1997).
Evaluation:
according to point C.5.3 of TCVN 6295:1997.
For a
seamless cylinder (of a capacity between 12 and 55 l), rely on the increase in
volume or decrease in weight of the cylinder shell to reduce the working
pressure of the cylinder or reject it according to the provisions in point 4.10
of TCVN 6156:1996.
Note: The
volumetric expansion test on seamless cylinders shall be conducted together
with the strength test.
c) Remove
and clean the test medium; dry the inside of the cylinder.
d)
Install the tested valves on the cylinder.
6. Step
6: Tightness test
a) Test
medium: Air or inert gas.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
c) For
seamless cylinders: Fill the cylinders with compressed air or inert gas to a
pressure of 50% to 60% of the maximum working pressure, hold this pressure for
01 minute.
d) Check
the tightness of the connectors, valve joints, etc. of the cylinders with soap
solution or in a specialized tank. Leaking cylinders must be treated and their
tightness must be re-tested.
Evaluation:
- For
welded cylinders: carry out evaluation according to point 9.2 of TCVN
6292:2013;
- For
seamless cylinders: carry out evaluation according to according to point C.6.3
of TCVN 6295:1997.
7. Step
7: Degassing and vacuuming
If a
cylinder is passed, proceed to completely degas the cylinder, dry its outside;
vacuum and fill the cylinder with shielding gas (if required).
8. Step
8: Checking tare weight of cylinders
a) Weigh
each cylinder and determine its tare weight (carry out evaluation according to
point 10.2 of TCVN 6292:2013). Check and compare it with the tare weight
stamped by the manufacturer on the cylinder;
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
c) For
seamless cylinders: carry out evaluation according to according to point 4.10
of TCVN 6156:1996.
9. Step
9: Processing inspection results
a)
Prepare an inspection record and a list of cylinders and cylinder batches which
contain sufficient information according to the form specified in the
Appendices to this inspection procedure.
b)
Approve the inspection record:
Mandatory
participants in the process of approving the inspection record include:
- When
inspecting cylinders at the inspecting organization's facility:
+
Facility's head directly inspecting cylinders;
+
Inspectors supervising the inspection of cylinders;
+ Head of
the technician team directly inspecting cylinders.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
- When
inspecting cylinders at the establishment:
+ Its
representative or person authorized by the establishment;
+ Person
assigned to witness the inspection;
+
Inspectors conducting the inspection.
As the
record is approved, the inspectors, the witness, and the representative of the
establishment or a person authorized by the establishment shall append their
signatures and seals (if any) on the record. The record shall be made
into two (02) copies, each party shall keep 01.
c) Write the brief inspection result to the profile of the
cylinder batch (including full names of the inspectors and the date of
inspection).
d) Affix
an inspection symbol:
- Stamp
information about inspection results on the handle or shoulder of each cylinder
in the correct size and in the same row in the following order: Symbol of the
inspecting organization-month/year of inspection-month/year of next inspection
(according to point 14.4 of TCVN 6294:2007 or point 4.12 of TCVN 6156:1996).
Such
information must not cover existing numbers on the cylinder’s handle or
shoulder.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
- For gas
cylinders filled with gas as specified in clause 1 Article 6 of this inspection
procedure, the inspection symbol is not required to be affixed but is affixed
upon the next inspection.
d)
Rejected cylinders must have the thread on their neck damaged or have their
body drilled to prevent gas from being mistakenly filled into the cylinders.
Apply the rejection method specified in section 15 of TCVN 6294:2007 to carbon
steel gas cylinders or section 10 of TCVN 6871:2007 to
acetylene cylinders.
e)
Certify the inspection result: If an inspected cylinder passes the test, the
inspecting organization shall issue the certificate of inspection result to the
cylinder or cylinder batch within 05 working days from the date on which the
inspection record is approved.
g) If the
cylinder or cylinder batch fails the test, the regulations set out in points a,
b and c clause 9 of this Article shall be complied with and the inspection
record explicitly specifying the explanation for the failure shall be issued to
the establishment.
h)
Cooperate with the establishment in handling rejected cylinders as prescribed
in point d clause 9 of this Article. Dossiers on rejected cylinders must be
archived at the inspecting organization; the inspection record and notification
shall be sent to the employment authority of the area where the inspection
facility is located.
Article 9. Inspection interval
1. The
technical safety inspection interval is 05 (five) years.
2. For
cylinders that have been used for more than 20 (twenty) years and cylinders that
contain corrosive and toxic gases such as Chlorine, Hydrogen Sulfide, Methane
Chloride, Phosphine, Sulfuric Anhydride and Hydrogen Chloride, the technical
safety inspection interval is 02 (two) years.
3. For
cylinders that contain corrosive and toxic gases such as Chlorine, Hydrogen
Sulfide, Methane Chloride, Phosphine, Sulfuric Anhydride and Hydrogen Chloride
that have been used for more than 20 (twenty) years, the technical safety
inspection interval is 01 (one) year.
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
5. If the
inspection interval is shortened, the inspector shall specify explanation in
the inspection record.
6. If the
inspection interval is specified in national technical regulations, such
national technical regulations shall apply.
APPENDIX 01
SPECIMEN OF RECORD ON
INSPECTION OF TECHNICAL SAFETY OF INDUSTRIAL GAS CYLINDERS
(Name of the inspecting organization)
-------
THE SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
.............., [place], ………[date]
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
RECORD ON INSPECTION OF TECHNICAL SAFETY OF INDUSTRIAL GAS
CYLINDERS
No. .........................
Pursuant
to the Procedure for inspection of technical safety of gas cylinders No. QTKD:
06-2021/BLDTBXH promulgated together with the Circular No.
............/2021/TT-BLDTBXH dated ..., 2021 of the Ministry of Labor -
Invalids and Social Affairs.
We
are:
Representatives
of the inspecting organization:
1.…………………………… Inspector number:………………..……………..…..….
2.……………………………
Inspector number:…………………………..…..…..….
currently
working for: …………………………………………………………….……. (specify name of the inspecting
organization)
Registration
certificate No. ……………………………….……..…….
Individuals
witnessing the inspection and approving the record:
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
2………………………………….……
Position:………….........……………….
Have
inspected (names of cylinders):……………………. …………………………
Under
ownership/management of (name of the organization or individual owning/managing
cylinders):……….…………
……………………………………………………………………..………………………...
Address
(head office of the establishment):……………………………………………..………
Address
(location) of installation:…………………………………………………….……………
I - BASIC SPECIFICATIONS
- Name
and address of the manufacturer:……………………………………………………….
- Month
and year of manufacture:…………………………………………………………….…..
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
-
Quantity and list of inspected sample cylinders: ................................................................
- Name of
brand stamped on
cylinders:................................................................................
- Working
pressure: ………….. bar Test pressure: .........................................bar.
-
Capacity: ……………….liter Tare weight: ………………………kg.
-
Uses:………………….…......................................................................................
-
Previous inspection record No. (if any):……………….. dated:…………………… conducted by
(name of inspecting authority): ……………………..……………….………………..
II - FORMS OF INSPECTION
First time
□
Periodic
□
Unscheduled □
- Reason
for unscheduled inspection (if any):……………….………………………..…….
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
1.
Document and profile examination:
Item
Evaluation
Yes
No
Cylinder
profile and documents
Manufacturer’s
technical documentation (applicable to first inspection, evaluation under point
a section 1 Article 8 of Inspection Procedure QTKD :06-2021/BLDTBXH)
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Cylinder
factory acceptance record (applicable to first inspection, evaluation
under point a section 1 Article 8 of Inspection Procedure QTKD
:06-2021/BLDTBXH)
Previous
inspection documents: Previous inspection record and certificate of previous
inspection result
(Not applicable to first inspection)
Documents
on the use, operation and maintenance; inspection or examination record (if
any)
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Documents
on repair, post-repair acceptance record documenting the replacement of
pressure retaining components (if any)
Other
documents (if any)
(Specify
enclosed documents)
Result
evaluation:
- Remarks:……………………………………………………………..................................
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
2.
External technical inspection
-
Remarks:……………………………………………………………..................................
…………………………………………………………………………………………………..
-
Technical specifications stamped on the cylinder: …………………………………........
- Defects
- deformations: ……………………………….................………..…………
- Result
evaluation:
Passed ⬜
Failed ⬜
3.
Internal technical inspection
-
Remarks:……………..………………..……………………………………...........................
…………………………………………………………………………………………………..
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
- Metal
surface, welds (not applicable to dissolved acetylene cylinders):…....
- Porous
mass (for dissolved acetylene cylinders): ………………................…………..…
- Result
evaluation:
Passed ⬜
Failed ⬜
4.
Test:
Type of test
Test medium
Test pressure
(bar)
Holding time
(minute)
Strength
test
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Volumetric
expansion test
Tightness
test
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
-
Remarks:…………………………………………………………….......................
- Result
evaluation:
Passed ⬜
Failed ⬜
IV – CONCLUSION AND RECOMMENDATIONS
1. Batch (quantity
of cylinders) inspected: Passed ⬜
Failed ⬜
2. Has an
inspection symbol affixed at: …………………………………………….
3.
Working pressure: ……………………bar.
4.
Recommendations: ……………………………………………………………………………..
5.
Deadline for implementation of recommendations: …………………………………………………………….
V - INSPECTION INTERVAL
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
The
record is approved on……………………[date]
At (specify
the place of inspection): ………………………………………………………….../.
1- At
the inspecting organization's inspection facility:
HEAD OF FACILITY
(Signature, full name)
INSPECTOR
(Signature, full name)
TECHNICIAN
(Signature, full name)
2- At
the establishment:
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
WITNESS
(Signature, full name)
INSPECTOR
(Signature, full name)
APPENDIX 02
LIST OF INSPECTED SAMPLE
CYLINDERS
Cylinder
batch:
Quantity
of cylinders:
Manufacturing
number: From………………..to……………………………………………..……
User
(manager):
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
No.
Manufacturing number
Month and year of manufacturing
Manufacturer
Weight (Kg)
Capacity
(liter)
Result
Passed
Failed (Specify reason)
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
2
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
...
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
APPENDIX 03
LIST OF CYLINDERS NOT INCLUDED
IN BATCHES (OR LIST OF CYLINDER BATCHES)
Cylinder
batch:
Quantity
of cylinders not included in cylinder batches:
User
(manager):
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
No.
Manufacturing number
No.
Manufacturing number
No.
Manufacturing number
No.
Manufacturing number
1
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
2
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
...
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Note:
+ When a
cylinder batch is continuously numbered, the quantity of cylinders not included
in batches is small (since some cylinders were taken out by the manufacturer
for mechanical testing, destructive testing, etc.), write “DANH SÁCH CÁC CHAI
KHÔNG CÓ TRONG LÔ” (“LIST OF CYLINDERS NOT INCLUDED IN BATCHES”. When a
cylinder batch is not continuously numbered, write “DANH SÁCH LÔ CHAI” (“LIST
OF CYLINDER BATCHES”) and fully write numbers of cylinders in the batches.
+ If the
quantity of cylinders is small, write it in the record. An enclosed list of
cylinders is not required.
Note:
This list of cylinders must not be erased or modified and must bear a seal at
the upper left corner or seal on adjoining edges of pages.
APPENDIX 04
LIST OF INSPECTED CYLINDER
BATCHES
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Quantity
of cylinders:
Manufacturing
number: From………………..to……………………….
User
(manager):
(Enclosed with inspection record or certificate of
inspection No. …………, dated…)
No.
Manufacturing number
Month and year of manufactyuring
Manufacturer
Weight (Kg)
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
Passed
Failed (Specify reason)
1
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
3
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.
...
...
...
...
Hãy đăng nhập hoặc đăng ký Thành viên
Pro tại đây để xem toàn bộ văn bản tiếng Anh.