THE MINISTRY OF CONSTRUCTION
-------
|
SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom
– Happiness
----------
|
No. 10/2009/TT-BXD
|
Hanoi, June 15, 2009
|
CIRCULAR
GUIDING THE MANAGEMENT OF
INVESTMENT PROJECTS TO BUILD DORMITORIES FOR STUDENTS AND HOUSES FOR WORKERS IN
INDUSTRIAL PARKS AND LOW EARNERS
THE MINISTRY OF CONSTRUCTION
Pursuant to the
Government's Decree No. 17/2008/ND-CP on February 4th 2008,
defining the functions, tasks and powers of the Ministry of Construction;
Pursuant to the
Government's Decree No. 209/2004/ND-CP on December 16th 2004, on
management of construction work quality; and the Government's Decree No.
49/2008/ND-CP of April 18, 2008, amending and supplementing a number of
articles of the Government's Decree No. 209/2004/ND-CP on December 16th
2004, on management of construction work quality;
Pursuant to the
Government's Decree No. 90/2006/ND-CP on September 6th 2006,
detailing and guiding the Housing Law;
Pursuant to the
Government's Decree No. 99/2007/ND-CP on June 13th 2007, on the
management of construction investment expenses;
Pursuant to the
Government's Decree No. 12/2009/ND-CP on February 12th 2009, on the
management of construction projects;
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The Ministry of
Construction guides in detail the management of investment projects to build
dormitories for students and houses for workers in industrial parks and low
earners as follows:
Chapter
I
GENERAL
PROVISIONS
Article
1. Scope of regulation and subjects of
application
1. Scope of regulation
This Circular guides
the management of:
a/ Investment projects
to build dormitories for students of public and private universities, colleges,
professional secondary schools, and vocational colleges and intermediate
schools (below collectively referred to as training institutions) under the
Prime Minister's Decision No. 65/2009/QD-TTg of April 24, 2009, promulgating a
number of mechanisms and policies to build dormitories for leasing out to
students of universities, colleges and professional secondary and vocational
schools.
b/ Investment projects
to build houses for workers of consolidated industrial parks (including
industrial clusters), export-processing zones and economic zones (below
collectively referred to as houses for workers in industrial parks) under the
Prime Minister's Decision No. 66/ 2009/QD-TTg of April 24, 2009, promulgating a
number of mechanisms and policies to build houses for leasing out to workers in
industrial parks.
c/ Investment projects
to build houses for low earners in urban areas (below referred to as houses for
low earners) under the Prime Minister's Decision No. 67/2009/QD-TTg of April
24, 2009, promulgating a number of mechanisms and policies to build houses for
low earners in urban areas.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
This Circular applies
to organizations and individuals investing in house construction and engaged in
the elaboration of housing projects specified in Clause 1 of this Article.
Article
2. Identification of project investors
1. Projects to build student dormitories:
a/ State-funded
projects:
- Based on
characteristics of these projects and local realities, provincial-level
People's Committees shall appoint the following agencies to act as their
investors:
- Provincial-level
Construction Departments or agencies with the construction investment
management function, for projects to build consolidated dormitories (including
projects to build dormitories for school clusters within the campuses of
training institutions).
+ Training
institutions, for projects to build dormitories within the campuses of those
training institutions.
- Investors of
projects to build student dormitories of training institutions under the armed
forces shall be decided by managing agencies of those training institutions.
b/ Projects with other
funds:
Owners of investment
capital of projects to build student dormitories shall act as their investors.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
a/ Investors to build
worker housing infrastructure (grade-I investors):
Investors to deal in
industrial park infrastructure may be:
- Local industrial park
management units or,
- Industrial park
infrastructure enterprises.
b/ Housing project
investors (grade-II investors)
Investors of projects
to build houses for workers in industrial parks may be:
- Local industrial
park management units;
- Industrial park
infrastructure enterprises;
- Production
enterprises in industrial parks:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3. Projects to build
houses for low earners:
Owners of investment
capital of projects to build houses for low earners shall act as their
investors.
Article
3. Competence to evaluate and decide on
project investment
1. Projects to build
student dormitories:
a/ State-funded
projects:
- Provincial-level
People's Committees may decide on investment in state-funded projects to build
consolidated dormitories and dormitories within the campuses of training
institutions, which are on the list of projects submitted by the Ministry of
Construction to the Prime Minister for approval. Provincial-level Planning and
Investment Departments shall evaluate these projects.
- Managing agencies of
training institutions under the armed forces shall assign their attached units
or professional agencies to evaluate projects to build student dormitories of
those training institutions before deciding on their investment.
b/ Projects with other
funds: Investors shall evaluate and approve these projects.
2. Projects to build
houses for workers in industrial parks and low earners:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Article
4. Project implementation order
Projects to build
student dormitories and houses for workers in industrial parks and low earners
shall be implemented in the following order:
1. Investment
preparation stage:
a/ Investment deciders
identify and appoint investors of housing projects under Article 2 of this
Circular.
b/ Investors make a
written proposal to provincial-level People's Committees for in-principle
approval of investment (except state-funded projects to build student
dormitories). The forms of proposal and in-principle approval of investment are
in Appendix 1 to this Circular (not printed herein).
c/ Investors formulate
and submit construction investment projects to investment deciders for
approval.
d/ Investment deciders
evaluate and approve projects.
2. Investment stage:
a/ Investors carry out
procedures for land allocation or lease to implement projects.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Provincial-level
People's Committees shall pay compensation and clear grounds for projects to
build student dormitories and houses for workers of established industrial
parks.
- Grade-I investors
shall pay compensation and clear grounds for projects to build houses for
workers of industrial parks under construction.
- Grade-I investors of
projects to build new urban centers or apartment buildings shall pay
compensation and clear grounds for projects to build houses for low earners.
c/ Investors select
contractors and sign contracts on construction survey and designing.
d/ Contractors conduct
construction survey, investors take over construction survey result reports.
e/ Contractors make
working drawing designs and cost estimates and submit them to investors for
evaluation and approval.
f/ Investors select
contractors and sign construction contracts.
g/ Contractors build
works.
3. Operation of
completed projects:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b/ Investors make and
submit investment capital settlements to investment deciders for approval.
c/ Investors elaborate
schemes on lease of student dormitories and rents (for non-state funded
projects) and rents of houses for workers in industrial parks and submit them
to provincial-level People's Committees for approval. Rents of student
dormitories built under state-funded projects shall be set by provincial-level
People's Committees.
Investors shall
elaborate schemes on sale, lease and hire-purchase and house prices under
projects to build houses for low earners after they are evaluated by
provincial-level People's Committees.
d/ Contractors provide
work warranty and operators maintain works.
Chapter
II
ELABORATION,
EVALUATION AND APPROVAL OF HOUSE CONSTRUCTION INVESTMENT PROJECTS
Article
5. Elaboration of house construction
investment projects
1. Basis for project
elaboration:
Investors shall
elaborate house construction investment projects. When investors are incapable
of doing so, they shall hire capable consultants to elaborate house
construction investment projects under this Article.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Projects to build
student dormitories and houses for workers in industrial parks and low earners
shall be classified and grouped under the Government's Decree No. 12/2009/
ND-CP of February 12, 2009, on management of work construction investment
projects,
b/ Student
dormitories:
Projects to build
student dormitories shall be formulated on the following grounds:
- For state-funded
projects: the list of projects under the plan on student dormitories
construction already made by the Ministry of Construction and approved by the
Prime Minister.
- Construction
plannings and plans to build student dormitories of localities, ministries,
branches and training institutions.
- Written in-principle
investment approval of the provincial-level People's Committee of locality where
projects are built (except state-funded projects to build student dormitories).
c/ Houses for workers
in industrial parks:
Projects to build
houses for workers in industrial parks shall be formulated on the following
grounds:
- Local industrial park
development planning, urban construction planning and housing development
programs.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Written in-principle
investment approval of the provincial-level People's Committee.
d/ Houses for low
earners:
Projects to build
houses for low earners shall be formulated on the following grounds:
- Local urban
construction planning and housing development program.
- Local needs,
conditions and characteristics.
- Written in-principle
investment approval of the provincial-level People's Committee.
e/ In addition to the
grounds specified at Points a. b. c and d of this Clause, projects to build
student dormitories and houses for workers in industrial parks and low earners
shall be formulated in accordance with regulations, standards, this Circular
and other relevant regulations.
2. Project contents:
a/ Explanation:
A project explanation
must cover the following major contents:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Construction site:
To clearly state the project site and location.
- Land use need: To
determine the project's land use need based on the construction investment need,
construction regulations and standards and this Circular.
- To describe the work
construction size and area and work items of the project.
- Solutions:
+ Site clearance plan
(if the project site is not yet cleared).
+ Plan on
infrastructure construction support (if any): including supports for technical
and social infrastructure works.
+ Architectural plan:
To state the project's conformity with construction and architecture plannings
and landscape of the project area.
+ Plan on project
management, operation and use: To specify modes of sale, lease and hirepurchase.
+ Project
implementation schedule: To clearly set investment phases and implementation
time and schedule of each phase.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ Total investment: To
be determined under current regulations on management of construction
investment expenses (Decree No. 99/2007/ND-CP of June 13. 2007. on management
of work construction investment expenses) and other relevant regulations on
designing, construction material use norms and capital investment ratios.
- Funds for
implementation: To clearly state funding sources: from the central or local
state budget: soft loans or capital of the investor.
- Other supports and
incentives.
b/ Basic design:
- Explanation:
Explanation of a basic
design must cover the following major contents:
+ Description of the
project site; locations and sizes of work items; connection of technical infrastructure
inside and outside the project area.
+ Designing plan;
total ground plan: To apply the construction density and land use coefficient
1.5 times the levels under construction regulations (depending on localities
and work construction sites).
+ Living area norms
(including axiliary area):
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
* Houses for workers
in industrial parks: minimum 5 m2/person; maximum 8 persons/
apartment.
* Houses for low
earners: maximum 70 m2/apartment.
+ Use coefficient (use
area: including living area and areas of other functional sections/
construction floor area) for houses of different categories: from 0.7-0.8.
+ Lists of major
designing regulations and standards: To mainly apply domestic standards.
+ To apply standards
on domestic medium construction materials.
- Drawings including:
+ Drawing on the
project's total ground plan.
+ Drawing on
architectural plans of main works.
+ Drawing on
connection of technical infrastructure inside and outside the project area.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. Investors shall
submit project dossiers to persons with investment-deciding competence for
evaluation and approval. Such a dossier comprises:
a/ Proposal for
project evaluation, made according to the form in Appendix 2 to this Circular
(not printed herein);
b/ House construction
investment project;
c/ Written
in-principle investment approval of the provincial-level People's Committee.
2. The key unit
appointed by the investment decider to evaluate projects under Article 3 of
this Circular shall evaluate projects and submit evaluation results to the
investment decider for approval.
3. When evaluating a
project, the key unit shall hold a meeting to obtain a provincial-level Construction
Department's opinions on basic design (when the provincial-level Construction
Department is the investor, such opinions are not required) and opinions of
other agencies in charge of electricity supply, water supply and drainage and
fire prevention and fighting. The key unit shall send the project dossier to
concerned agencies at least 10 working days before such meeting. Opinions of
agencies at the meeting will be official opinions on the project and shall be
recorded in writing.
Article
7. Contents of evaluation of house
construction investment projects
A key unit's project
evaluation covers:
1. Elements to
guarantee project feasibility:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b/ Ground clearance
capacity (if ground clearance is required).
c/ Capacity to supply
electricity, water, etc.
2. Economic efficiency
of the project (except state-funded projects to build student dormitories).
3. Basic design:
a/ Conformity with the
construction planning, architecture and landscape of the project area;
b/ Appropriateness of
technical infrastructure connection;
c/ Application of
designing regulations and standards;
d/ Capability
conditions of project formulation and basic design-making consultants.
When a model design is
applied, evaluation of basic design is not required.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Key units shall submit
dossiers of house construction investment projects to persons with
investment-deciding competence for approval.
1. A project dossier
comprises:
a/ A proposal made
according to the form in Appendix 3 to this Circular (not printed herein);
b/ Project dossier and
additional documents of the investor (if any) under Article 6 of this Circular;
c/ Minutes of the
project evaluation meeting specified in Clause 3, Article 6 of this Circular;
2. Decisions to
approve house construction investment projects shall be made according to the
form in Appendix 4 to this Circular (not printed herein).
Article
9. Time frames for elaboration,
evaluation and approval of house construction investment projects
1. The time for
elaborating a state-funded project to build student dormitories is maximum 20
working days.
2. The time for
evaluating and approving a house construction investment project is maximum 20
working days after receiving valid dossiers.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. Elaboration of
construction investment projects is not required for houses with a total
investment of under VND 15 billion (exclusive of land use levy), for which only
techno-economic reports are required.
2. The order to
elaborate, contents and evaluation of, and competence to approve,
techno-economic reports on house construction investment comply with the
Construction Ministry's Circular No. 03/2009/TT-BXD of March 26, 2009, and this
Circular.
Chapter
III
IMPLEMENTATION
OF HOUSE CONSTRUCTION INVESTMENT PROJECTS
Article
11. House construction design
1. Two-step designing,
which includes basic and working drawing designing, is required for projects to
build student dormitories and houses for workers in industrial parks and low
earners.
2. One-step designing,
which is working drawing designing, is required for state-funded projects to
build student dormitories which apply model designs or works for which only
techno-economic reports are required.
3. Investors shall
elaborate, evaluate and approve working drawing designs under the Government's
Decree No. 12/2009/ND-CP of February 12, 2009, on management of work
construction investment projects.
4. The time for making
working drawing designs of state-funded projects to build student dormitories
is maximum 30 working days.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Article
12. Construction permits
After drawing designs
are approved, investors of house construction investment projects under this
Circular may start construction without applying for a construction permit, but
shall notify such to the local construction management agency at least 7 days
before starting construction.
Article
13. Selection of construction
consultants and contractors
1. Investors may implement
state-funded projects to build student dormitories if they are capable or
appoint, negotiate and sign contracts with capable consultancy organizations to
formulate projects, make designs, supervise construction, provide supplies and
materials and build works.
When contractor
designation is applied, the value of the consultancy contract may be reduced by
5% at most; and contracts on equipment and goods supply and construction, by 2%
at most compared with the approved cost estimates.
2. Investors may
implement projects funded with other sources if they are capable or decide
modes to select capable contractors to implement projects.
3. Designation of
capable EPC (engineering, procurement and construction) contractors is
encouraged.
4. Contract signing:
Investors may select modes to sign contracts with contractors to perform jobs
of the project on the basis of mutual agreement.
5. The time for
carrying out procedures and negotiating for contract signing for state-funded
projects which apply contractor designation is maximum 20 working days.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. During
construction, involved parties shall manage construction quality, volumes and
schedules and environmental safety and sanitation under the Construction Law,
Decree No. 12/2009/ND-CP, Decree No. 209/2004/ND-CP, Decree No. 49/2008/ND-CP
and relevant guiding documents.
2. Before being put
into use, constructed houses must be inspected and certified for quality
conformity by capable independent consultancy organizations under regulations.
Article
15. Management of house construction
investment expenses
1. The estimation and
management of expenses for housing construction investment projects comply with
the Government's Decree No. 99/2007/ND-CP of June 13, 2007, on management of work
construction investment expenses and guiding documents.
In case of designating
EPC contractors to implement state-funded projects to build student
dormitories, when negotiating for contract signing, the contract value may be
temporarily determined based on the approved total investment. The EPC contract
value shall be officially determined based on the cost estimates of works under
a project, but must not exceed its approved total investment.
2. The advance and payment
for projects comply with law and contractual terms.
3. The settlement of
investment capital complies with current regulations.
Article
16. Project management methods
1. When approving
projects, investment deciders may decide on their management methods based on
the project size and nature and investors' capacity to manage projects.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Chapter
IV
ORGANIZATION
OF IMPLEMENTATION
Article
17. The Ministry of Construction shall:
1. Make a list of
state-funded projects to build student dormitories based on reports of
ministries, branches and provincial-level People's Committees and submit it to
the Prime Minister for approval.
2. Assume the prime
responsibility for, and coordinate with ministries, branches and provincial-level
People's Committees in, elaborating investment plans to build student
dormitories and houses for workers in industrial parks and low earners for the
2009-2015 period and submit them to the Prime Minister for approval.
3. Guide, urge and examine
the investment in building dormitories for students and houses for workers in
industrial parks and low earners, review their implementation and propose
mechanisms to address arising problems to the Prime Minister.
Article
18. Provincial-level People's
Committees shall:
1. Elaborate and
approve plans to implement projects to build student dormitories of training
institutions regardless of their managing agencies, and projects to build
houses for workers in industrial parks and low earners in their localities.
2. Direct the
implementation of the investment programs to build houses under this Circular
in their localities.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Article
19. Concerned ministries and branches
shall:
1. Elaborate and
approve plans to implement projects to build student dormitories of training institutions
under their investment competence.
2. Coordinate with
provincial-level People's Committees in directing the implementation of
projects to build student dormitories of training institutions under their
management according to this Circular and relevant legal documents.
3. Biannually and
annually report the implementation and arising problems and propose their
solutions to the Ministry of Construction for settlement or sum-up for report
to the Prime Minister for settlement.
Article
20. Implementation provisions
1. This Circular takes
effect on August 1, 2009.
2. Any problems
arising from the implementation of this Circular should be reported to the
Ministry of Construction for consideration and settlement.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
ANNEX 1 (FORM 1)
Enclosed with the Circular No.
10/2009/TT-BXD dated June 15th 2009 of the Ministry of Construction,
guiding the management of projects of investment in dormitories for students,
houses for workers in industrial parks, and houses for low earners
Name of the investor:
SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom
– Happiness
----------
APPLICATION
FOR THE PERMISSION TO INVEST IN THE CONSTRUCTION PROJECT … [NAME OF THE
PROJECT]
To: The People’s Committee of …
Pursuant to ……………………………………………………
1. Name of the investor:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3.
Phone:
Fax:
4. Applies for the permission from the People’s Committee of:
5. To invest in: (name of the project)
6. At: (location of the project)
7. Estimated land area:
8. Construction area:
9. Floor area (for each kind of constructions):
10. Scale of the project: (number of rooms, apartments, used area, etc.)
11. Construction density:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
13. Construction coefficient:
14. Financial capacity, experience in investment and construction
management:
15. Other issues:
Requests the People’s Committee of … to permit … (name of the investor) to
invest in this project. If the People’s Committee of … permits, … (name of the
investor) shall make and send a construction project to competent authorities
for appraisal and approval as prescribed.
(Location and date)
The investor
(Signature and seal)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
ANNEX 1 (FORM
2)
Enclosed with the Circular No.
10/2009/TT-BXD dated June 15th 2009 of the Ministry of Construction,
guiding the management of projects of investment in dormitories for students,
houses for workers in industrial parks, and houses for low earners
The People’s Committee of …
SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom
– Happiness
----------
On the permission for the investment
(Location and date)
To: (name of the investor)
After considering the Application of …. for the permission to invest in the
project ..................
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The People’s Committee of ……. permits ….. to make the
construction project …………. as follows:
1. Name of the investor:
2. Name of the project:
3. Construction location:
4. Position of project’s land:
5. Project’s land area:
6. Construction area:
7. Construction density:
8. Land use coefficient:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
10. The criteria and requirements for zoning and architecture:
11. The application of regulations and standards:
12. The buyers and lessees:
13. Total investment:
14. Capital sources
15. Proposals and request:
16. Other issues:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(Signature)
ANNEX 2
Enclosed with the Circular No.
10/2009/TT-BXD dated June 15th 2009 of the Ministry of Construction,
guiding the management of projects of investment in dormitories for students,
houses for workers in industrial parks, and houses for low earners
Investor
SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom
– Happiness
----------
No.
(Location and date)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
To: (the agency that permits the investment)
- Pursuant to the Government's Decree No. …….… dated … on the management
of construction projects;
- Other relevant legal basis;
The investor applies for the appraisal of the housing construction project
… (for students, workers, or low earners). In particular:
1. Name of project:
2. Investor:
3. The organization that advises on the project making
4. Person in charge of making the project:
5. Objectives of the construction project:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
7. Construction location:
8. Land area:
9. Construction plan (fundamental design):
10. Type and class of construction:
11. Plan for land clearance and resettlement (if any):
12. Total investment in the project:
Total:
Including:
- Construction expenses:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Land clearance and resettlement expenses (if any):
- Other expenses:
- Provisionary expenses:
13. Capital sources:
14. The form of sale, lease, hire-purchase:
15. Sale prices, hire-purchase prices, and rents
16. Project management method:
17. Project duration:
18. Incentives and special mechanisms:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
20. Conclusion:
The investor requests … (the agency that permits the investment) to
appraise and approve the construction project ………………….
Investor
(Signature, full name, position, and
seal)
ANNEX 3
Enclosed with the Circular No.
10/2009/TT-BXD dated June 15th 2009 of the Ministry of Construction,
guiding the management of projects of investment in dormitories for students,
houses for workers in industrial parks, and houses for low earners
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom
– Happiness
----------
No.
(Location and date)
APPLICATION
FOR THE APPROVAL FOR HOUSING CONSTRUCTION PROJECT …… (NAME OF PROJECT)
To: (the agency competent to approve the
investment)
(The appraising agency) ……. received the application for the
appraisal and approval for the housing construction project (for students,
workers, or low earners) No. …… dated ……. of ……..
- Pursuant to the Government's Decree No. ……… dated ………. on the management
of construction projects.
- Pursuant to …………………………………
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. After the appraisal, … (the appraising agency) reports the result of
the project appraisals, in particular:
a) Name of
project :
Type of project: (for students, etc.)
b) Investor:
c) Construction location:
d) Land area:
2. Legality of the application for the appraisal and approval:
a) The basis for making the project:
b) The contractor that advises on the project making:
c) The contractor that creates the fundamental design
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
dd) The applicable regulations and standards:
e) The application for the appraisal includes:
g) Relevant legal documents: (Certificate of business registration,
handover record, written approval for the investment, minutes of meetings with
branches, etc.)
3. Summary of the primary contents of the project: (as in the application
for the appraisal and approval for the project of the investor)
4. Summary of opinions from relevant agencies:
5. Remarks and assessments about the project:
a) The necessity and investment objectives:
b) The conformity with the master plan:
c) The conformity with the list of projects approved by the Prime Minister
and provincial People’s Committees (if any)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
dd) The compliance to the applicable construction standards and
regulations.
e) The consistency of the design with the Regulations, standards, and this
Circular.
g) The conformity of the architecture with master plan for construction,
architecture, and scenery approved by competent authorities.
h) The plan for using and running the projects: the plan for sale, lease,
hire-purchase, etc.
i) The assessment of environmental impacts, and measures for fire safety
k) Plan for land clearance and resettlement (if any)
l) Total investment, capital source, the capital raise capacity, the
repayment plan, applicable to the projects that require capital recovery, and
financial targets. Analysis of socio-economic efficiency.
m) The construction duration, the stages, and progress
6. Proposals of investors:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
8. The shortcomings of the project; the responsibility and deadline for
resolving:
9. Specific proposals:
Requests … (the agency that permits the investment) to consider and approve
(or not approve) the project. The investor must be informed whether the project
is approved or not approved.
Head of the agency that appraises the
project
(Signature and seal)
ANNEX 4
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Approving agency
SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom
– Happiness
----------
No.
(Location and date)
DECISION
OF … ON THE APPROVAL FOR THE HOUSING CONSTRUCTION PROJECT …………. (NAME OF THE
PROJECT)
(Name of the person or agency that
gives the approval)
- Pursuant to functions, tasks, and organizational structure of
……………………..;
- Pursuant to the Government's Decree No. ……… dated ………. on the management
of construction projects.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Pursuant to …………………………………
After considering the Application for the approval for the housing
construction project …….. of made by … (the appraising agency) and the report
on the appraisal result
Considering the request of …… in the Application No. ………… dated ……………. And
the report on the appraisal result of ………………,
DECIDES:
Article 1. Approving the housing construction project …………… with
the following primary contents:
1. Name of project:
2. Investor:
3. The organization that advises on the project making
4. Person in charge of making the project:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
6. Contents and scale of construction:
7. Construction location:
8. Land area:
9. Construction plan (fundamental design):
10. Type and class of construction:
11. Plan for land clearance and resettlement (if any):
12. Total investment in the project:
Total investment:
Including:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Equipment expenses:
- Land clearance and resettlement expenses (if any):
- Other expenses:
- Provisionary expenses:
13. Capital sources:
14. Sale prices, hire-purchase prices, rents, etc.
15. Project management method:
16. Project duration:
17. Incentives:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Article 2. Implementation organization.
Article 3. Responsibility of relevant agencies for the implementation
of this Decision./.
The approving agency
(Signature, full name, position, and
seal)