This Circular will be implemented as follows:
- The procuring entity must post the decision on approval of revision to e-ITB (including amendment contents) and an updated version of e-ITB which has already been revised.
- Revision must be completed within at least 03 working days prior to the closing time provided that bidders have enough time to prepare a complete e-bid document (E-BD);
If not, the closing time must be extended.
After all revisions have already been made, the system must send a notification to the bidder who has clicked "follow" on the e-bid notification (E-BN) page, a subsidiary page of this online system.
It is noted that bidders are advised to frequently keep themselves updated with any correction made on the system in order to prepare correct e-BDs and meet e-ITB requirements.
For more details, please read through the Circular No. 04/2017/TT-BKHDT which is set to enter into force from March 1, 2018.
>> CLICK HERE TO READ THE ARTICLE IN VIETNAMESE
2.071