05/2016/TT-BXD
|
Hanoi,
March 10, 2016
|
CIRCULAR
PROVIDING GUIDANCE ON DETERMINATION OF THE UNIT LABOR COST IN
THE CONSTRUCTION COST MANAGEMENT
Pursuant to the Government's
Decree No. 62/2013/ND-CP dated June 25, 2013 on defining the functions, tasks,
powers and organizational structure of the Ministry of Construction;
Pursuant to the Government’s
Decree No. 32/2015/ND-CP dated March 25, 2015 on the construction cost
management;
At the requests of the
Director General of the Department of Construction Economics and the Director
General of the Institute of Construction Economics;
The Minister of Construction
hereby promulgates this Circular on providing guidance on determination of the
unit labor cost in the construction cost management,
Article
1. Scope of application
This Circular shall provide the
guidance on determination of the unit labor cost in the construction cost
management, including: total investment, construction cost estimate, contract
estimate, construction price, contract price and construction price index.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. Agencies, organizations and
individuals related to the management of the construction cost of investment
and construction projects using state budget funds or non-budget state funds,
and investment projects under the form of public-private partnership (PPP) shall
be governed under the provisions of this Circular.
2. Agencies, organizations and
individuals related to the management of the construction cost of projects funded
by other capital sources are encouraged to implement this Circular.
Article
3. Rules for unit labor cost determination and adjustment
1. The unit labor cost
determined under the guidance of this Circular must comply with the following
principles:
a) Correspond with the rank-based
levels of workmanship in the construction cost estimation system.
b) Correspond with the general
level of wages of construction workers (including allowances for disadvantaged living
conditions) in specific local labor market provided that such wage level is not
lower than the minimum region-based salary stipulated by the Government.
c) Correspond with characteristics
and the nature of work of each construction worker.
d) Be adequate to cover compulsory
payment of several expenses that belong to workers’ liability as regulated (including
social insurance, medical insurance and unemployment insurance).
2. The unit labor cost shall be
adjusted if there is a fluctuation of general wage level of construction
workers in the labor market.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The unit labor cost of a
worker who directly performs construction works shall be determined according
to the following formula:
Where:
- GNC: the unit
labor cost paid to a worker who directly performs construction works in a
working day.
- LNC: the monthly input
base salary which is used to calculate the unit labor cost paid to a worker who
directly performs construction works in a working day, including allowances
according to characteristics and the nature of construction works according to
market factors and types of insurance premiums paid by the worker as regulated
(including social insurance, medical insurance and unemployment insurance). The
input base salary is stated in the Table 1 Annex 1 of this Circular for
reference.
- HCB: the salary
coefficient which is applied to workers who directly perform construction works
and regulated in Annex 2 of this Circular.
- t:
26 working days per a month.
Article
5. Implementation
1. People’s committees of
central-affiliated cities or provinces shall comply with the guidance stated in
this Circular to direct the construction departments to cooperate with relevant
agencies in the investigation, survey, determination and announcement of the
unit labor cost for using as the basis for preparing and managing construction
costs of local projects.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3. The Ministry of Construction
shall adjust the input base salary (LNC) regulated in Annex 1
herewith when there is a fluctuation of the general wage level of construction
workers of above 10%.
Article
6. Transitional provision
1. Where the unit labor cost
included in the total investment and construction cost estimate of concerned
construction project is approved prior to the effective date of this Circular,
the investment decision-maker of such project shall decide the implementation
of this Circular.
If the construction contract is concluded before the effective
date of this Circular, terms and conditions of the signed contract shall apply.
2. Where several construction
projects are allowed to apply the salary rate and several allowances of
particular characteristics by competent authorities, such application shall be
continued until the construction phase ends and such projects are put into
operation.
Article
7. Effect
1. This Circular shall take
effect as of May 01, 2016 and replace the Circular No. 01/2015/TT-BXD dated
March 20, 2015 of the Ministry of Construction on the guidance on determination
of the unit labor cost in the construction cost management.
2. During the implementation of
this Circular, difficulties shall be reported to the Ministry of Construction for
consideration and settlement./.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Annexes
enclosed to the Circular No. 05/2016/TT-BXD dated March 10, 2016 of the
Ministry of Construction
ANNEX 1
Table 1: The input base salary used to determine the
unit labor cost of construction worker (LNC)
Unit:
VND/month
Region
I
Region
II
Region
III
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2,350,000 ÷ 2,530,000
2,150,000 ÷ 2,320,000
2,000,000 ÷ 2,154,000
1,900,000 ÷ 2,050,000
Notes:
- Regions where the region-I,
II, III and IV input base salary rates are applied shall comply with the
Government’s regulations on classification of regions and the minimum region-based
salary.
- The aforesaid input base
salary is determined by dividing the investigated actual average salary by
corresponding salary coefficient regulated in the Annex 2 herewith. The
investigated actual average salary includes compulsory payments of insurance
premiums made by the worker to the State and excludes those made by the
employer (social insurance, health insurance, union dues and unemployment
insurance).
ANNEX 2
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Ranks
of construction worker
1
2
3
4
5
6
7
Group
I
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1.55
1.83
2.16
2.55
3.01
3.56
4.20
Group
II
Salary
coefficient
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2.07
2.44
2.86
3.37
3.96
4.65
Notes:
Group 1: Workers who perform
the following works:
- Woodwork,
bricklaying, metal work (except for asphalt concrete), formwork, completion
work and earthwork (excavation and backfilling);
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Operation of construction
machinery and equipment (earthwork machinery, rammer, lifting equipment,
drilling equipment, pile driver, pump, welder, etc.). This group includes manual
workers who directly perform construction works.
Group 2: Workers
who perform construction works other than those are specified in group I
Table
2: Ranks and salary coefficients of field engineers
Rank
of engineer
1
2
3
4
5
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
7
8
Salary
coefficient
2.34
2.65
2.96
3.27
3.58
3.89
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
4.51
Notes:
As for engineers who
directly perform certain construction works such as survey and testing defined
in the current cost estimation system, their ranks and salary coefficients
shall apply the table 2.
Table
3: Ranks and salary coefficients of artisans
Rank
of artisan
1
2
Salary
coefficient
6.25
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Notes:
As for artisans who directly
perform certain works defined in the current cost estimation system, their ranks
and salary coefficients shall apply the table 3.
Table
4: Ranks and salary coefficients of vehicle operators
Rank
of vehicle operator
Group
of vehicles
1
2
3
4
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Group
1
2.18
2.57
3.05
3.60
Group
2
2.51
2.94
3.44
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Group
3
2.99
3.50
4.11
4.82
Notes:
1. Group 1: Box truck, dump
truck and water truck with the maximum gross vehicle weight of 7.5T; truck
crane with the maximum lifting capacity of 7.5T; vacuum truck used to remove
drilling mud; pickup truck; 7-seater van used for performing construction
survey; vacuum truck with the maximum gross vehicle weight of 10 tonnes;
pipeline pressure testing equipment with air compression of 170CV.
2. Group 2: Box truck, dump
truck and water truck with the maximum gross vehicle weight rating from 7.5T to
below 25T; truck crane with the lifting capacity rating from 7.5T to below 25T:
concrete mixer truck with drum volume of below 14.5 m3; concrete
pump truck; asphalt sprayer truck.
3. Group 3: Dump truck with the
maximum gross vehicle weight of more than 25T; tractor truck with towing
capacity of more than 200CV; concrete mixer truck with drum capacity of more
than 14.5 m3; truck crane with lifting capacity of more than 25T.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Table
5.1: Ranks and salary coefficients of captains, second-in-command
officers, 1st assistant engineers and 2nd assistant
engineers of ships, canoes, floating cranes, floating pile driving hammers and
pile driving vessels
Title
Group
1
Group
2
Rank
1
2
1
2
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. Captain
3.73
3.91
4.14
4.36
2. 1st
second-in-command officer, 1st assistant engineer
3.17
3.30
3.55
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3. 2nd
second-in-command officer, 2nd assistant engineer
2.66
2.81
2.93
3.10
Notes:
1. Group 1: Ship or canoe with
main engine capacity rating from 5CV to 150CV.
2. Group 2: Ship or canoe with
main engine capacity of more than 150CV; floating crane; pile driving vessel.
Table
5.2: Ranks and salary coefficients of seafarers, technical
and electro-technical officers
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Rank
1
2
3
4
Salary
coefficient
1. Seafarer
1.93
2.18
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2.83
2. Technical or
electro-technical officer
2.05
2.35
2.66
2.99
Table
5.3: Ranks and salary coefficients of operators of river
suction or backhoe dredgers
Title
by dredger groups
Dredger
with the maximum suction capacity of 150m³/h
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Dredger
with the suction capacity of above 300m3/h, or with the maximum backhoe
capacity of 300m³/h
Rank
1
2
1
2
1
2
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. Captain
3.91
4.16
4.37
4.68
4.88
5.19
2. Chief technical
officer
3.50
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
4.16
4.37
4.71
5.07
3. Chief
electro-technical officer
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
4.36
4. 2nd
assistant engineer, 1st backhoe technician, second-in-command
officer
3.48
3.71
4.09
4.30
4.68
4.92
5. 2nd
backhoe technician
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3.50
3.73
3.91
4.37
4.68
Table
5.4: Ranks and salary coefficients of operators of marine
suction, backhoe and grab dredgers
Title
by dredger groups
Capacity
rating from 300m3/h to 800m3/h
Capacity
of more than 800m3/h
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1
2
1
2
Salary
coefficient
1. Captain of trailing
suction hopper dredger
5.19
5.41
5.41
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. Chief technical
officer, captain of backhoe, suction or grab dredger
4.92
5.19
5.19
5.41
3. Chief
electro-technical officer of suction or backhoe dredger; 1st
technician, 2nd second-in-command officer of trailing suction
hopper dredger; 2nd backhoe technician of backhoe, suction or grab
dredger
4.37
4.68
4.68
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
4. 2nd
assistant engineer; 1st backhoe technician of backhoe, suction or
grab dredger
4.68
4.92
4.92
5.19
5. Second-in-command
officer of backhoe dredger, 2nd backhoe technician of suction
dredger
4.16
4.37
4.37
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Table
6: Ranks and salary coefficients of engineer divers
Title
Rank
1
2
3
4
Salary
coefficient
1. Engineer diver
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3.28
3.72
4.15
2. Class-I engineer
diver
4.67
5.27
3. Class-II engineer
diver
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
ANNEX 3
METHOD FOR DETERMINATION OF THE LABOR COST IN THE
CONSTRUCTION MARKET
1. Principle for survey and
determination of the labor cost in the construction market:
- The labor cost in the
construction market (referred to as the market labor cost) refers to the wage which
is paid to a worker for performing a given work and determined in the market of
a specific region or area. There are different labor cost levels in
corresponding with different types of works. The labor cost is also determined on
the basis of worker's level of workmanship and prestige, and the relationship
between supply and demand in the labor market. The average market labor cost
for a specific work is arithmetic average of different market labor costs for
performing such work.
- The unit labor cost included
in the direct cost of the construction cost estimate refers to the average unit
labor cost in the market in a specific region, paying to a worker who works 8
hours per day, and such cost excludes the employer’s compulsory payments of
insurance premiums to the state (social insurance and health insurance premiums,
union dues and unemployment insurance premium), which are included in the
general cost.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. Steps for performing the investigation
and survey of the labor cost unit in the construction market:
2.1. Classification of
regions: The classification of regions for performing the survey shall comply
with the Government's regulations on minimum region-based salary.
2.2. Determination of individuals
subject to the investigation and survey:
- Investigate and survey workers
who directly perform construction works of economic sectors in the labor
market, including main workers and marginal workers for a specific work.
- Investigate and survey main
workers and marginal workers of economic sectors through the employers.
2.3. Method of investigation
and survey: interview or send survey questionnaires to surveyees.
2.4. The minimum quantity of
surveyees for regional labor cost must be 15 main workers and 15 marginal
workers, representing group works at concentrated residential regions and
construction sites. As for regions in which required quantity of surveyees is
not satisfied, the survey shall be carried out on actual quantity of invited surveyees.
2.5. Handing
investigated/surveyed figures:
- Method: dividing “the sum of
the algorithmic average of labor cost levels paid to main workers and the
algorithmic average of labor cost levels paid to marginal workers” by 2, this
labor cost is equivalent to that of worker ranked 3.5/7. Labor cost levels of
other ranks of workers shall be determined on the basis of the labor cost of
worker ranked 3.5/7 and tables of ranks and salary coefficients stated in the
Annex No. 2.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Where:
- : Average
unit labor cost of the skilled worker;
- ai: Unit labor
cost of the skilled worker i;
- :
Average unit labor cost of the helper;
- bi: Unit labor
cost of the helper i;
- n: The quantity of main
workers and marginal workers who are investigated and surveyed in a specific
region, n ≥ 15 (except for cases require quantity of surveyees is not
satisfied).
- :
Average unit labor cost of workers ranked 3.5/7.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
No.
Rank
of worker
Group-I
worker’s salary coefficient
(VND/working
day)
Working
days during month (t)
Lnc
(VND/month)
Announced
unit labor cost
(VND/working day)
(1)
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(3)
(4)
(5)
(6)=(4)*(5)/(3)
(7)=(6)*(3)/(5)
1
1/7
1.55
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
144,798
2
2/7
1.83
26
170,955
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3/7
2.16
26
201,783
4
3.5/7
2.355
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
26
2,428,875
220,000
5
4/7
2.55
26
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
6
5/7
3.01
26
281,189
7
6/7
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
26
332,569
8
7/7
4.2
26
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
392,357
- Unit labor cost levels of
group-II workers shall be determined as per the method of determining unit
labor cost levels of group-I workers as stated in the aforesaid example.
2.6. As for remote regions
and islands, people’s committees of provinces shall consider and adjust labor
cost levels of construction workers with the coefficient at most at 1.2 of the
average labor cost levels determined as regulated in section 2.5.