THE
MINISTRY OF TRANSPORT
-------
|
SOCIALIST
REPUBLIC OF VIET NAM
Independence - Freedom – Happiness
---------
|
No.
1745/QD-BGTVT
|
Hanoi,
August, 03, 2011
|
DECISION
APPROVING
THE DETAILED MASTER PLAN ON THE SEAPORT GROUP IN SOUTHEAST VIETNAM (GROUP 5)
THROUGH 2020, WITH ORIENTATIONS TOWARD 2030
THE MINISTER OF TRANSPORT
Pursuant to the November 26,
2003 Construction Law; Pursuant to the June 14, 2005 Maritime Code of Vietnam;
Pursuant to the Government’s
Decree No. 51/2008/ND-CP of April 22, 2008, defining the functions, tasks,
powers and organizational structure of the Ministry of Transport;
Pursuant to the Government’s
Decree No. 92/2006/ND-CP of September 7, 2006, on elaboration, appraisal,
approval and management of socio- economic development master plans, and Decree
No. 04/2008/ND-CP of January 11, 2008, amending and supplementing a number of
articles of Decree No. 92/2006/ND-CP;
Pursuant to the Prime
Minister’s Decision No. 2190/QD-TTg of December 24, 2009, approving the master
plan on development of Vietnam’s seaport system through 2020, with orientations
toward 2030;
Pursuant to the Government
Office’s Notice No. 132/TB-VPCP of June 2, 2011, on conclusions of Prime
Minister Nguyen Tan Dung at a cabinet meeting on implementation of the detailed
master plan on Group 5 of seaports;
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
At the proposal of the
standing body of the Appraisal Council and the director of the Planning and
Investment Department,
DECIDES:
Article 1. To approve the
detailed master plan on the seaport group in Southeast Vietnam (Group 5)
through 2020, with orientations toward 2030, with the following principal
contents:
1. Scope of the master plan
Group 5 consists of seaports in coastal provinces and a city in the
southeastern region, including Ho Chi Minh City, and Dong Nai, Ba Ria - Vung
Tau and Binh Duong provinces, and ports on Soai Rap river in Long An and Tien
Giang provinces.
2. Development viewpoints and
objectives a/ Development viewpoints:
- To utilize and bring into full
play natural and social conditions of the region for developing seaports in Cai
Mep - Thi Vai, Ben Dinh - Sao Mai and Hiep Phuoc areas and such potential
locations as Long Son… so as to efficiently exploit land areas for building
ports, raising the capacity to accommodate large-tonnage ships and promoting
the potential of international transshipment of group-5 seaports.
- To develop seaports of Group 5
in combination with synchronous connection of road, railway and internal
waterway infrastructure facilities, creating a driving force and promoting the
development of coastal economic zones and urban centers and large industrial
parks in Ho Chi Minh City, Dong Nai, Ba Ria - Vung Tau, Binh Duong and Binh
Phuoc provinces and adjacent provinces. To harmoniously develop special-use
wharves for bulky or liquid goods, farm produce,… so as to handle various kinds
of goods of the whole region.
- To reserve land and water
surface areas for planning the development of general and container wharves or
wharves for special-use goods in service of the whole region.
- To intensify the application
of advanced and modern technologies to management and operation of seaports,
first of all, large ones in Cai Mep -Thi Vai (Ba Ria - Vung Tau), Cat Lai and
Hiep Phuoc (Ho Chi Minh City), to raise the operation efficiency and meet
socio-economic development requirements of the southern dynamic economic
region.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- To mobilize to the utmost all
social resources, especially from the private sector and foreign direct
investment for developing seaports and seaport common-use infrastructure
facilities.
- To develop ports in a
sustainable manner, associating port development with environmental protection
and protection of the natural ecosystem and avoiding bad impacts on social and
daily-life activities of inhabitants in the region. The development and
operation of regional seaports must be associated with the protection of the
eco-environment in Ganh Rai bay, Can Gio submerged eco-forests and submerged
forests along Thi Vai river, avoiding bad impacts on tourism potentials of Ho
Chi Minh City and Vung Tau city.
- To develop seaports to meet
also security and national defense requirements.
b/ Development objectives and
orientations
- General objectives:
+ To rationally locate seaports
in the group so as to promote their combined efficiency; and at the same time
to create a balanced and synchronous development of seaports and infrastructure
facilities related to their zone of attraction, and combine seaport development
with industrial and service development to create a driving force for economic
development, security and national defense.
+ To meet the requirements for
relocating the port system on Sai Gon river and Ba Son shipyard in order to
reduce the traffic flow and congestion in downtown Ho Chi Minh City.
+ To support the development of
industrial parks and export processing zones in the region and concurrently
facilitate the urban development in order to accelerate the regional industrialization
and modernization from now through 2020, with orientations toward 2030.
+ To form and develop modern
international gateway ports and regional major ports to follow the development
trends of Vietnam’s and the world’s ocean shipping industry, attracting part of
cargoes transshipped through the region.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ To ensure a cargo throughput
at the planning points of time as follows:
. 169 - 200 million tons/year by
2015;
. 235 - 317 million tons/year by
2020;
. 393 - 681 million tons/year by
2030;
Of which, the container cargo
throughput at the planning points of time are as follows:
. 7,563 - 9,563 thousand
TEU/year by 2015;
. 12,125 - 17,995 thousand
TEU/year by 2020;
. 23,370 - 46,229 thousand
TEU/year by 2030;
And the number of seaborne
passengers to arrive at these seaports at the planning points of time are as
follows:
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
. 418.1 - 539,4 thousand
arrivals/year by 2020;
. 917,1 - 1,335.8 thousand
arrivals/year by 2030;
+ To accommodate seagoing ships
of the following types: sundry and bulky cargo ships of between 10,000 and
60,000 DWT, container ships of an equivalent tonnage of between 10,000 and
100,000 DWT, crude oil tankers of up to 300,000 DWT, oil product tankers of
between 10,000 and 50,000 DWT, and passenger ships of between 50,000 and
100,000 GRT.
3. Contents of the master plan
a/ Detailed planning of seaports
in the group
Group 5 consists of three
seaports: Vung Tau seaport (including also Con Dao seaport), Dong Nai seaport
(including also Binh Duong wharf area) and Ho Chi Minh City seaport (including
also wharf areas of Long An and Tien Giang provinces on Soai Rap river).
- Ho Chi Minh City seaport: This
is a national and regional major general seaport (class I), which consists of
the following main wharf areas: the wharf area on Sai Gon river; Cat Lai wharf
area on Dong Nai river; the wharf area on Nha Be river; Hiep Phuoc wharf area
on Soai Rap river; and the wharf areas in Long An and Tien Giang provinces on
Soai Rap river.
The seaport’s projected cargo
throughput by 2015, 2020 and 2030 will reach around 91.843 - 100.465, 105.825 -
132.57 and 160.133 - 271.289 million tons/year, respectively, of which
container cargo volume will be around 4.183 - 4.908, 4.844 - 6.976 and 8.557 -
17.576 million TEU/year, respectively.
The number of international
passengers expected to arrive at the seaport by 2015, 2020 and 2030 will reach
164.2 - 200.5, 202.8 - 261.5 and 444.7 -647.7 thousands/year, respectively.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ The wharf area on Sai Gon
river: This area consists of 11 wharves/piers for ships of between 20,000 and
30,000 DWT. This wharf area will be relocated and have its utilities
transformed under the Prime Minister’s Decision No. 791/QD-TTg of August 12,
2005. Khanh Hoi wharf will be partially transformed into a domestic passenger
landing stage and a maritime service center. Wharves not to be relocated will
only be renovated and upgraded.
+ Cat Lai wharf area (on Dong Nai
river): This area consists of 9 wharves/piers for ships of up to 30,000 DWT.
This is the major container wharf area of the seaport in the near future.
+ Nha Be wharf area (on Nha Be
river): This area consists of 10 wharves/piers for ships of between 20,000 -
30,000 DWT. The wharves on Nha Be river are planned to be renovated and
upgraded (not expanded) for ships of up to 30,000 DWT. A new passenger landing
stage will be built in Phu Thuan (downstream Phu My bridge) for ships of 50,000
GRT.
+ Hiep Phuoc wharf area (on Soai
Rap river): This is the major wharf area of the seaport in the future, mainly
to handle general and container cargoes for ships of 50,000 DWT and container
ships of 4,000 TEU. It will have several special-use wharves for ships of between
20,000 - 30,000 DWT to directly serve adjacent industrial establishments.
+ Long An and Tien Giang wharf
areas (on Soai Rap river): This areas have wharves functioning as general
cargo, oil and gas service and LPG special-use wharves which can accommodate
ships of up to 50,000 DWT or larger tonnage suitable to their channels’
capacity.
- Dong Nai seaport: This is a
national and regional major general seaport (class I), which consists of the
following functional wharf areas: Long Binh Tan and Binh Duong wharf areas (on
Dong Nai river); Phu Huu wharf area (on Dong Nai river and Long Tau - Nha Be
river), Ong Keo wharf area (Long Tau river and Dong Tranh river); Go Dau and
Phuoc An wharf areas (on Thi Vai river).
The port’s projected cargo
throughput by 2015, 2020 and 2030 will reach around 19.663 - 21.135, 43.186 -
53.111 and 71.763 - 112.992 million tons/year, respectively, of which container
cargo volume will be around 620 - 775, 2,280 - 2,850 and 4,413 - 7,543 thousand
TEU/year, respectively.
Detailed planning of main
functional wharf areas is as follows:
+ Phuoc An and Go Dau wharf
areas (on Thi Vai river): This is the major wharf area of the seaport, mainly
accommodating general and container ships of up to 60,000 DWT (Phuoc An) and
30,000 DWT (Go Dau), and having several special-use wharves which can
accommodate ships of between 6,500 - 12,000 DWT in direct service of adjacent
industrial establishments.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ The wharf area on Dong Nai
river: This area consists of wharves for general, container and bulky cargo
ships of up to 5,000 DWT and special- use wharves for ships of 1,000 DWT in
Long Binh Tan area (Dong Nai province) and Binh Duong port for ships of up to
5,000 DWT.
- Vung Tau seaport: This is a
national and international gateway general seaport (class IA), which consists
of the following main functional wharf areas: Go Dau and Tac Ca Trung wharf
areas; Phu My and My Xuan wharf areas; Cai Mep and Sao Mai-Ben Dinh wharf
areas; Long Son wharf area; Vung Tau - Dinh river and Con Dao wharf areas.
The port’s projected cargo
throughput by 2015, 2020 and 2030 will reach around 57.257 - 78.043, 85.669 -
131.088 and 161.491 - 296.291 million tons/year, respectively, of which
container cargo volume will be around 2.76 - 3.88, 5.001 - 8.169 and 10.4 -
21.11 million TEU/year, respectively.
The number of seaborne
international passengers expected to arrive at the seaport by 2015, 2020 and
2030 will reach 174.4 - 213.1, 215.4 - 277.9 and 472.4 - 688.1 thousand
arrivals/year, respectively.
Detailed planning of main
functional wharf areas is as follows:
+ Go Dau and Tac Ca Trung wharf
areas: This area is for general and container ships and can accommodate ships
of up to 30,000 DWT.
+ Phu My and My Xuan wharf areas
(Thi Vai river): These areas are for handling general and container cargoes of
ships of between 50,000 and 80,000 DWT or between 4,000 and 6,000 TEU. To
further study the possibility of renovating and expanding channels to
accommodate ships of between 60,000 and 120,000 DWT (loading capacity of
between 4,000 and 10,000 TEU) in Phu My and ships of up to 60,000 DWT in My
Xuan. These areas have several special-use wharves to serve industrial and
service establishments.
+ Cai Mep and Sao Mai - Ben Dinh
wharf areas: These areas are major wharf areas of the seaport, mainly for
handling container cargoes exported or imported on ocean shipping routes and
attracting international transshipment containers. Cai Mep area will
accommodate ships of between 80,000 and 100,000 DWT (loading capacity of
between 4,000 and 10,000 TEU). To further study the possibility of renovating
channels to accommodate ships of over 100,000 DWT in Cai Mep. Sao Mai - Ben
Dinh area will accommodate container ships of between 80,000 DWT (loading
capacity of 6,000 TEU) and over 100,000 DWT and have landing stages for
international tourists carried by ships of up to 100,000 GRT.
+ Long Son wharf area: This area
functions as a special-use wharf area of the petrochemical complex having a
terminal to receive crude oil for ships of 300,000 DWT and a wharf of between
30,000 and 50,000 DWT for import of other materials and export of products. The
southeastern coastline section of the area will be reserved for building a
general wharf for long-term development of the region.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ Con Dao wharf area: This area
functions mainly as a general cargo wharf and a passenger landing stage for Con
Dao, which can accommodate ships of between 2,000 and 5,000 DWT. A maritime and
oil and gas service wharf will also be built for ships of up to 10,000 DWT.
b/ Orientations for the planned
relocation in subsequent periods
A main road linking ports along
Saigon river from Tan Phu My bridge to Cat Lai, Thu Duc, Long Thanh, Vung Tau
and Dong Nai industrial parks will be built. As a result, these ports will
continue operating like at present and will only be studied for relocation
after 2020 if necessary.
(A detailed list of seaports in
the group and their sizes and functions and locations and scopes of logistics
centers is specified in the Appendix and the master plan dossier attached to
this Decision, not printed herein).
c/ Solutions to moored wharves
The location of moored wharves
on channels is just temporary to meet practical needs in the near future in
areas where conditions do not permit the building of solid wharves. Therefore,
the building of moored wharves must be incorporated in the development planning
and suitable to operations of solid wharves. When the construction of solid
wharves is completed, investors of moored wharves shall remove these moored
wharves as required to assure safe and effective operation of solid wharves.
d/ Planned renovation and
upgrading of channels
- Saigon - Vung Tau channel: To
renovate some bending sections, maintain a depth and a maritime signaling
system of Long Tau channel for ships of 30,000 DWT which can enter and leave
the seaport all the day on the high tide.
- Soai Rap channel: From now to
2015, this channel will accommodate fully loaded ships of up to 30,000 DWT and
partially loaded ships of 50,000 DWT. In subsequent periods, to consider
dredging the channel for fully loaded ships of up to 50,000 DWT and partially
loaded ships of over 50,000 DWT.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Cai Mep - Thi Vai channel: To
study and determine the largest tonnage of ships which can enter wharf areas in
the coming period. Projected ship tonnage which can be accommodated by wharf
areas are as follows:
+ Cai Mep wharf area: For ships
of between 80,000 and over 100,000 DWT and container ships of between 4,000 and
8,000 TEU;
+ Phu My wharf area (Thi Vai):
For ships of between 60,000 and 100,000 DWT and container ships of between
4,000 and 8,000 TEU;
+ Phuoc An and My Xuan wharf
areas: For ships of up to 60,000 DWT;
+ Go Dau wharf area: For ships
of up to 30,000 DWT.
+ Dinh river channel (from buoy
zero to VietsovPetro port): To maintain the conditions for stable operation for
ships of 10,000 DWT.
e/ Priority projects through
2015
- Port access channels:
+ Cai Mep - Thi Vai: channel: To
comprehensively study the channel section for ships of over 100,000 DWT
entering Cai Mep wharf area; ships of up to 100,000 DWT to enter wharves of Phu
My area; ships of up to 60,000 DWT entering wharves of My Xuan and Phuoc An
areas; and for ships of up to 30,000 DWT entering wharves of Go Dau area.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Wharves:
(1) For general and container
wharves
+ Vung Tau international wharves
in Sao Mai - Ben Dinh: These wharves are mainly for international container
transshipment for ships of between 80,000 DWT (6,000 TEU) and over 100,000 DWT.
+ Lower Cai Mep general and
container wharves: These wharves accommodate ships of between 80,000 DWT (6,000
TEU) and over 100,000 DWT.
+ Hiep Phuoc downstream wharf
area: This is the major general and container wharf area of Ho Chi Minh City
which can accommodate ships of up to 50,000 DWT (4,000 TEU) and may be upgraded
to accommodate ships of over 50,000 DWT to suit the development of channels.
(2) For special-use wharves
+ To invest in a special-use
wharf area for Long Son petrochemical refinery: This area is exclusively for
crude oil, oil products and imported materials.
- Port-linking roads
+ National highway 51 (Dong Nai
- Ba Ria-Vung Tau): To complete the upgrading and expansion of this national
highway to link Cai Mep - Thi Vai port system with the regional transport
network.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ Phu Huu - Ong Keo (Dong Nai)
inter-port road: To invest in this road in order to accelerate the formation
and development of Phu Huu - Ong Keo wharf area.
+ Provincial road 25B to Cat Lai
port (Ho Chi Minh City: To complete the upgrading and expansion of this road to
link Hanoi expressway with Cat Lai wharf area.
+ Road to wharves in Hiep Phuoc
area: To continue investing in and completing the North-South axial road to
Hiep Phuoc area and trunk roads in Hiep Phuoc industrial park linking to
wharves.
+ Roads linking to Long An and
Tien Giang wharf areas: To study the building of roads linking to Long An and
Tien Giang wharf areas.
4. Policies, mechanisms and
solutions for implementation
a/ Regarding investment in port
development in general
- To step up mobilization of all
social resources for investment in developing seaport infrastructure facilities
in the forms of PPP, BOT, BT,… To intensify investment promotion, encourage and
create favorable conditions for all economic sectors at home and abroad to
invest in developing seaports in the prscribed forms.
- To concentrate state budget
sources on investing in public infrastructure facilities (navigable channels
and breakwaters for common use) connected to important seaports. Wharf
infrastructure facilities will be built with funds lawfully mobilized from
enterprises. All infrastructure and port- linking infrastructure facilities of
seaport and wharves recommended by investors, including general wharves, will
be built with capital raised by these investors themselves.
- To study and permit on a pilot
basis foreign partners to invest in loading and unloading equipment and hire
other entities to operate port infrastructure facilities invested with domestic
capital (associated with transfer of advanced technologies).
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- To step up the building of
wharves and wharf areas for common use in economic zones and industrial parks
so as to promote the investment efficiency and use of natural resources in the
coastline for building seaports. To reserve land areas for port development,
each of a width of 500 - 700 meters along big rivers with potential for port
development (Cai Mep - Thi Vai, Soai Rap, Long Tau, Nha Be, Dong Nai,…). To
reserve appropriate land areas behind seaports for building goods distribution
centers with logistic functions.
- To further step up
administrative reform in the management of investment and operation of seaports
toward simplicity and modernity; to study and apply on a pilot basis the model
of “port management office” at seaports where conditions permit; to facilitate
the location of working offices of maritime port authorities and specialized
state management agencies in new port areas in order to ensure prompt state
management at seaports; and to encourage investors in economic zones and
industrial parks to invest in seaport infrastructure and port-linking
infrastructure facilities.
b/ Mechanisms and policies for
and organization of the planned relocation
- Mechanisms and policies for
and organization of the planned relocation of ports on Saigon river and Ba Son
shipyard shall continue complying with the Prime Minister’s Decision No.
791/QD-TTg of August 12, 2005 and other relevant directing documents.
- Capital amounts obtained from
transformation of utilities, conversion of land use rights and sale of
workshops and other works shall be used under the Prime Minister’s Decision No.
74/2005/QD-TTg of April 6, 2005, on use of proceeds from the transfer of land
use rights, sale of workshops and other works upon relocation of economic
organizations’ offices, production or business establishments under the master
plan, and the Prime Minister’s Decision No. 46/2010/QD-TTg of June 24, 2010,
promulgating the financial regulation applicable to the relocation of ports on
Saigon river and Ba Son shipyard.
- Other regimes and policies
(land rents, taxes, use of preferential credit loans,…) for to-be-relocated
enterprises comply with current regulations.
In case of necessity, problems
arising in the course of relocation must be reported to the Steering Committee
for implementation of the plan on relocation of ports on Saigon river and Ba
Son shipyard for settlement or to the Prime Minister, for issues beyond local
authorities’ competence.
c/ Mechanisms to promote
internationally transshipped cargoes
For Vung Tau seaport with the
role of an international gateway seaport of class 1A in the South Vietnam, in
addition to its principal function of handling exports and imports on ocean
shipping routes of the whole South Vietnam, it is necessary to study and
acquire fundamental conditions of infrastructure, management and operation,
financial, banking and other specialized services for raising competitiveness,
attraction and handling of internationally transshipped cargoes of the region.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1. The Vietnam Maritime
Administration shall:
- Coordinate with
provincial-level People’s Committees and related agencies in publicizing and
managing the implementation of the approved master plan.
- Report to the Ministry of
Transport for consideration and decision on addition and adjustment of
functions and sizes of seaports and wharves.
- For potential seaports and
wharves: Summarize and report on practical needs and proposals of investors and
provincial-level People’s Committees to the Ministry of Transport for
consideration and decision.
- Annually coordinate with local
administrations and related agencies in inspecting the implementation of the
master plan, reviewing and proposing measures to handle projects implemented
not under the master plan, and reporting them to the Ministry of Transport.
- Assign the Vietnam Maritime
Administration to study a general mechanism for management, operation and
development of infrastructure facilities and other related services in order to
attract internationally transshipped cargoes for Cai Mep and Sao Mai - Ben Dinh
wharf areas, enabling them to compete with international transshipment ports in
the region.
2. Ministries, sectors and
provincial-level People’s Committees shall:
- Direct investors in
formulating projects to build, renovate and upgrade seaports and navigable
channels in line with the approved master plan and in accordance with current
regulations on construction investment management.
- Provincial-level People’s
Committees shall base themselves on the approved master plan to closely manage
and use for proper purposes land areas reserved for building seaports; arrange
land areas for synchronous development of seaports and port-linking
infrastructure facilities, service areas behind seaports, logistic and maritime
service areas in order to assure favorable conditions for seaport operation;
and coordinate with the Ministry of Transport in organizing harmonious traffic,
ensuring that port- linking traffic does not conflict with urban traffic.
...
...
...
Bạn phải
đăng nhập hoặc
đăng ký Thành Viên
TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN.
Mọi chi tiết xin liên hệ:
ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ For wharf areas and wharves
for different types of cargoes and built by different investors:
Provincial-level People’s Committees shall direct functional agencies in
working out and submitting detailed master plans to the Vietnam Maritime
Administration for appraisal and reporting to the Ministry of Transport for
consideration and approval.
+ For other wharf areas and
wharves: Provincial-level People’s Committees shall direct investors or
functional agencies in working out and submitting detailed master plans to the
Ministry of Transport and the Vietnam Maritime Administration for study and
updating in the detailed master plan on the seaport group, and manage these
master plans.
Article 3. This Decision
takes effect on the date of its signing.
Article 4. The director
of the Office, the Chief Inspector, directors of the departments, the Ministry
of Transport, the director of the Vietnam Maritime Administration, and heads of
related organizations and related individuals shall implement this Decision.-
MINISTER
OF TRANSPORT
Ho Nghia Dung