CIRCULAR
GUIDELINES ON SOME
CONTENTS OF PRE-FEASIBILITY STUDY REPORTS AMD FEASIBILITY STUDY REPORTS OF
INVESTMENT PROJECTS IN THE FORMS OF PUBLIC-PRIVATE PARTNERSHIP, BUILD-
OPERATE-TRANSFER CONTRACTS IN TRANSPORT SECTOR
Pursuant to the Law on Public-Private
Partnership Investment dated June 18, 2020;
Pursuant to the Law providing amendments to the
Law on Public Investment, the Law on Public-Private Partnership Investment, the
Investment Law, the Housing Law, the Law on Electricity, the Law on
Enterprises, the Law on Excise Duties, and the Law on Civil Judgment
Enforcement dated January 11, 2022;
Pursuant to the Government’s Decree No. 28/2021/ND-CP
dated March 26, 2021 prescribing financial management mechanism of
public-private partnership projects;
Pursuant to the Government’s Decree No.
35/2021/ND-CP dated March 29, 2021 providing guidelines for implementation of
the Law on public-private partnership investment;
Pursuant to the Government’s Decree No.
12/2017/ND-CP dated February 10, 2017 defining the functions, tasks, powers and
organizational structure of the Ministry of Transport;
At the request of the Director of the Public -
Private Partnership Investment Project Management Department;
...
...
...
Please sign up or sign in to your
TVPL Pro Membership to see English documents.
Chapter I
GENERAL PROVISIONS
Article 1. Scope
1. This Circular provides guidelines on some
contents of pre-feasibility study reports and feasibility study reports of
investment projects in the forms of public-private partnership (PPP), build-
operate-transfer contracts (hereinafter referred to as “BOT contract”) in
transport sector, including: socio-economic efficiency indicators; rates of
return on equity of investors; indicators for evaluation of quality of
infrastructure works/systems provided by project enterprises; depreciation
periods of infrastructure works/systems.
2. With regard to BTO (Build-Transfer-Operate)
contracts, BOO (Build-Own-Operate) contracts, O&M (Operate & Manage)
contracts, BTL (Build-Transfer-Lease) contracts, BLT (Build-Lease-Transfer)
contracts, and mixed contract, pre-feasibility study reports and feasibility
study reports shall be formulated in accordance with the provisions of this
Circular and relevant laws, and include contents suitable for the type of
contract, specific characteristics of each sector and of each project.
Article 2. Regulated entities
This Circular applies to organizations and
individuals involved in the formulation of pre-feasibility study reports and
feasibility study reports of investment projects in the forms of PPP and BOT
contract in the transport sector.
Chapter II
SOCIO-ECONOMIC EFFICIENCY INDICATORS; RATES OF RETURN
ON EQUITY OF INVESTORS; INDICATORS FOR EVALUATION OF QUALITY OF INFRASTRUCTURE
WORKS/SYSTEMS PROVIDED BY PROJECT ENTERPRISES; DEPRECIATION PERIODS OF
INFRASTRUCTURE WORKS/SYSTEMS
...
...
...
Please sign up or sign in to your
TVPL Pro Membership to see English documents.
1. Socio-economic efficiency indicators of a
project include: Economic Net Present Value (ENPV),
Benefit-Cost Ratio (BCR), and Economic Internal Rate of Return
(EIRR). The values of these indicators shall be calculated in accordance with the
provisions of Part IV Form No. 01 in Appendix II and Part IV Form No. 01 in
Appendix III enclosed with the Government’s Decree No. 35/2021/ND-CP dated
March 29, 2021.
2. Socio-economic benefits of projects
Socio-economic benefits of a project are divided
into the following groups:
a) Group of benefits which can be quantified and
converted into monetary values, including: benefits of reduction of costs of
vehicle operation, benefits of time savings for goods and passenger transport.
b) Group of benefits which can be quantified but
cannot be valued, including: benefits of environmental improvement due to
minimization of environmental impacts regarding emissions, dust, and noise,
benefits of promotion of economic growth, creation of jobs, promotion of
movement capacity of goods an passengers, and benefits of reduction of traffic
accidents.
c) Group of qualitative benefits, including:
benefits of the increased connectivity between regions, benefits of job
creation and improvement of living standards of residents in areas where the
project is located.
d) The entities in charge of formulating
pre-feasibility study reports and feasibility study reports may include in such
reports the benefits other than those specified in Points a, b, c Clause 2 of
this Article which must be suitable for the type of contract, specific
characteristics of each sector/project and comply with relevant laws.
e) In case there are ungrounded for determining
benefits which can be quantified and converted into monetary values for
calculating socio-economic efficiency indicators of a project, the entities in
charge of formulating pre-feasibility study reports and feasibility study
reports may evaluate socio-economic efficiency of the project based on other
groups of socio-economic benefits.
Article 4. Rates of return on equity of
investors
...
...
...
Please sign up or sign in to your
TVPL Pro Membership to see English documents.
Costs of equity with due account taken of risk and
inflation element shall be calculated using the following formula:
i = iv
+ f
Where:
i: costs of equity of investors;
iv: interest on borrowed investment
fund, which shall be determined on the basis of the lending interest rates on
medium and long-term loans quoted by at least 03 commercial banks, and interest
rates on borrowed fund of similar projects which are employed for formulating
the financial plan included in the pre-feasibility study report/ feasibility
study report (if any). The interest on borrowed investment fund shall be
determined at the nearest time within 03 months before formulating the
pre-feasibility study report/feasibility study report;
f: inflation rate which is determined according to
the average CPI (consumer price index) of the latest 10 years quoted by the
General Statistics Office of Vietnam while excluding the years in which the CPI
value changes significantly.
2. Rate of return on equity of investors
Pursuant to regulations of law and based on
socio-economic conditions as well as specific characteristics of the project,
the entity in charge of preparing the project shall calculate the return on
equity of the investor under the financial plan which is included in the
pre-feasibility study report/feasibility study report, provided that:
a) The return on equity shall not exceed the costs
of equity of investors (i) prescribed in Clause 1 of this Article;
...
...
...
Please sign up or sign in to your
TVPL Pro Membership to see English documents.
Article 5. Indicators for evaluation of quality
of infrastructure works/systems provided by project enterprises
The indicators for evaluation of quality of
infrastructure works/systems provided by project enterprises include the level
of compliance of the infrastructure work/system with regulations on survey,
design, construction, operation and maintenance laid down in technical
regulation/standard applicable to each project and regulations of law on
quality of construction works. Such level of compliance shall be evaluated in
accordance with specialized laws.
Article 6. Depreciation periods of
infrastructure works/systems
Depreciation periods of infrastructure
works/systems shall comply with Clause 5 Article 1 of the Circular No.
147/2016/TT-BTC dated October 13, 2016 of the Ministry of Finance of Vietnam.
Chapter III
IMPLEMENTATION
Article 7. Transition
1. In case investment guidelines of a project have
been decided by competent authorities but the project has yet to be approved
before the effective date of this Circular, the entity in charge of formulating
the project shall make revisions to the project’s feasibility study report in
accordance with the provisions of this Circular provided such revisions shall
not cause changes in the project’s investment guidelines.
2. In case investment guidelines of a project have
been decided by competent authorities and the project has been approved before
the effective date of this Circular, such decision on investment guidelines and
the project approval decision shall prevail.
...
...
...
Please sign up or sign in to your
TVPL Pro Membership to see English documents.
1. This Circular comes into force from November 01,
2022.
2. If any legislative documents referred to in this
Circular are amended, supplemented or superseded, the new ones shall prevail.
Article 9. Implementation organization
Chief of the Ministry Office, Chief Inspector of
the Ministry, Director General of Directorate for Roads of Vietnam, Directors
of Departments/ Administrations affiliated to the Ministry of Transport,
Directors of Project Management Boards affiliated to the Ministry of Transport,
Directors of Provincial Departments of Transports, heads of relevant
authorities/agencies and relevant individuals shall implement this Circular./.
PP. MINISTER
DEPUTY MINISTER
Nguyen Duy Lam