Statistics
- Documents in English (15490)
- Official Dispatches (1344)
Popular Documents
-
Decision No. 1431/QD-TTg dated November 19, 2024 on approving investment guidelines for... (1)
-
Announcement No. 6150/TB-BLDTBXH dated December 03, 2024 on Lunar New Year, National Day,... (1)
-
Circular No. 83/2024/TT-BCA dated November 15, 2024 on regulations for the development,... (1)
-
Circular No. 33/2024/TT-BGTVT dated November 14, 2024 on management of prices of ferry services... (1)
-
Circular No. 63/2024/TT-BCA dated November 12, 2024 on inspection, control, and handling... (1)
-
Decision No. 2690/QD-NHNN dated December 18, 2024 on prescribing interest rates imposed... (1)
-
Official telegram No. 121/CD-TTg dated November 26, 2024 on further promotion of developing... (1)
|
VĂN
PHÒNG CHÍNH PHỦ
-------
|
CỘNG
HÒA XÃ HỘI CHỦ NGHĨA VIỆT NAM
Độc lập - Tự do - Hạnh phúc
---------------
|
Số: 67/TB-VPCP
|
Hà
Nội, ngày 07 tháng 02
năm 2013
|
THÔNG BÁO
KẾT
LUẬN CỦA PHÓ THỦ TƯỚNG HOÀNG TRUNG HẢI - TRƯỞNG BAN CHỈ ĐẠO VỀ ĐẦU TƯ THEO HÌNH
THỨC ĐỐI TÁC CÔNG - TƯ
Ngày 01 tháng 02 năm 2013, tại Văn
phòng Chính phủ, Phó Thủ tướng Hoàng Trung Hải - Trưởng Ban Chỉ đạo về đầu tư
theo hình thức đối tác công - tư (PPP) đã chủ trì phiên họp lần thứ hai của Ban
Chỉ đạo. Tham dự cuộc họp có đại diện các Bộ, ngành là thành viên Ban Chỉ đạo.
Sau khi nghe Bộ Kế hoạch và Đầu tư báo cáo và ý kiến phát biểu của các đại biểu
dự họp, Phó Thủ tướng Hoàng Trung Hải - Trưởng Ban Chỉ đạo đã kết luận như sau:
1. Thời gian qua, Bộ Kế hoạch và Đầu tư (Cơ quan Thường trực Ban chỉ đạo) đã làm được nhiều
việc, là cơ sở quan trọng cho triển khai mô hình PPP như: tổ chức thực hiện
hoàn thiện hành lang pháp lý; trình Trưởng Ban ban hành Quy chế hoạt động của
Ban chỉ đạo; xây dựng Kế hoạch hoạt động năm 2013 của Ban
Chỉ đạo; công tác đào tạo tăng cường năng lực; xây dựng hướng dẫn sử dụng Quỹ
hỗ trợ phát triển dự án PPP... Thời gian tới, Bộ Kế hoạch và Đầu tư và các Bộ,
ngành tiếp tục tập trung khẩn trương sửa đổi Quyết định 71/2010/QĐ-TTg, sau khi
thực hiện thành công sẽ nâng cấp thành Nghị định của Chính phủ.
2. Trên cơ sở ý kiến tham gia của các
Thành viên Ban chỉ đạo, đồng ý thông qua Kế hoạch hoạt
động năm 2013 của Ban chỉ đạo. Yêu cầu các Bộ, ngành và địa phương rà soát, đề
xuất các dự án có tính khả thi (nằm trong quy hoạch phát triển, có khả năng thu
hồi vốn và hấp dẫn các nhà đầu tư...), chậm nhất ngày 10/3/2013 gửi Bộ Kế hoạch
và Đầu tư để tổng hợp Danh mục dự án đầu tư PPP, trình Trưởng Ban chỉ đạo phê
duyệt.
3. Một số nhiệm vụ trong thời gian
tới:
- Khẩn trương hoàn thiện việc kiện
toàn Tổ công tác liên ngành về PPP;
- Tăng cường tính chủ động, tích cực
phối hợp của các Bộ, ngành có đại diện là Thành viên Ban Chỉ đạo nhằm đẩy mạnh
việc thực hiện các nhiệm vụ chung của Ban Chỉ đạo cũng như các nhiệm vụ về PPP
thuộc lĩnh vực, ngành mình phụ trách.
- Các Bộ, ngành và địa phương thành
lập các bộ phận chuyên trách về PPP (Tổ, Ban PPP...) để quản lý và theo dõi dự
án.
- Bộ Tài chính khẩn trương hoàn tất
các thủ tục khoản vay 8 triệu EUR từ AFD; Ngân hàng Nhà nước Việt Nam khẩn
trương hoàn thiện việc công bố hiệu lực của khoản vay 20 triệu USD từ ADB cho
Quỹ hỗ trợ phát triển dự án PPP (PDF).
- Bộ Kế hoạch và
Đầu tư chủ trì, phối hợp với các Bộ, ngành và địa phương đẩy mạnh công tác đào
tạo, tăng cường năng lực về PPP.
- Về một số dự án cụ thể:
+ Dự án đường cao tốc Dầu Giây - Phan
Thiết: Văn phòng Chính phủ lấy ý kiến của các cơ quan liên quan, trình Thủ
tướng Chính phủ xem xét, quyết định.
+ Dự án đường cao tốc Biên Hòa - Vũng
Tàu: phía Nhật Bản đã nghiên cứu triển khai bằng nguồn vốn PSIF, vì vậy tiếp
tục triển khai theo mô hình này.
+ Dự án đường cao tốc Ninh Bình - Hà
Tĩnh (Bãi Vọt): Bộ Giao thông vận tải tiếp tục nghiên cứu triển khai theo mô
hình PPP và xác định thời điểm, phạm vi đầu tư phù hợp.
+ Dự án Nâng cấp nhà máy xử lý nước
thải tập trung khu công nghiệp An Nghiệp, tỉnh Sóc Trăng: Bộ Tài nguyên và Môi
trường phối hợp với Bộ Kế hoạch và Đầu tư và Ủy ban nhân
dân tỉnh Sóc Trăng nghiên cứu về khả năng cho vay đối với dự án và lãi suất ưu
đãi từ Quỹ Bảo vệ môi trường Việt Nam.
+ Dự án cung cấp các dịch vụ hậu cần
bệnh viện: Bộ Y tế lập Tổ công tác, phối hợp với Bộ Kế hoạch
và Đầu tư để tiếp tục triển khai các nội dung đã thống nhất với Công ty
Hellmann. Về nguyên tắc phải thực hiện theo pháp luật của
Việt Nam.
+ Dự án Ứng dụng
thương mại điện tử trong mua sắm chính phủ: Bộ Kế hoạch và
Đầu tư khẩn trương phê duyệt Báo cáo nghiên cứu khả thi
(FS), Hồ sơ mời thầu và tổ chức lựa chọn nhà đầu tư để sớm đưa Dự án vào hoạt
động.
+ Các dự án BOT ngành điện có thể sử
dụng Quỹ PDF để lập Báo cáo nghiên cứu khả thi (FS). Bộ Công Thương tổ chức đấu
thầu rộng rãi để lựa chọn nhà đầu tư.
Văn phòng Chính phủ xin thông báo để
Bộ Kế hoạch và Đầu tư và các cơ quan liên quan và biết, thực hiện./.
Nơi nhận:
- Thủ tướng, các Phó Thủ tướng;
- Các Bộ, cơ quan ngang Bộ, cơ quan thuộc CP;
- UBND các tỉnh, thành phố trực thuộc TW;
- VPCP: BTCN, các PCN, Cổng TTĐT, các Vụ: KTTH, TH, V.III, QHQT,
TKBT;
- Lưu: VT, KTN(3).
|
KT.
BỘ TRƯỞNG, CHỦ NHIỆM
PHÓ CHỦ NHIỆM
Phạm Văn Phượng
|
OFFICE OF
GOVERMENT
-------
|
SOCIALIST
REPUBLIC OF VIETNAM Independence
- Freedom – Happiness
----------
|
No.: 67/TB-VPCP
|
Hanoi,
February 07, 2013
|
ANNOUNCEMENT ON
CONCLUSION OF THE DEPUTY PRIME MINISTER HOANG TRUNG HAI – CHIEF OF STEERING
BOARD OF INVESTMENT IN THE PUBLIC-PRIVATE PARTNERSHIP FORM On February 01, 2013, at Office of
Government, Deputy Prime Minister Hoang Trung Hai - Chief of Steering Board of
Investment In The Public-Private Partnership Form (PPP) presided over second
session of the Steering Board. The meeting has participation of representative
of Ministries, sectors being members of Steering Board. After listening report
of the Ministry of Planning and Investment and opinions of delegates
participating in the meeting, Deputy Prime Minister Hoang Trung Hai - Chief of
Steering Board concluded as follows: 1. In past time, the Ministry of
Planning and Investment (Standing agency of the Steering Board) has done many
missions which are important basis for carrying out the PPP model, including:
Organizing to finalize legal corridor; submitting the chief for promulgation of
Regulation on operation of the Steering Board; formulating the 2013 action plan
of the Steering Board; training and improving capability; formulating guide on
development support fund use for PPP projects, etc. In next time, the Ministry
of Planning and Investment and Ministries, sectors shall continue to
expeditiously amend the Decision No. 71/2010/QD-TTg, after its implementation
is successful, it shall be upgraded to a Government’s Decree. 2. On the basis of opinions of
members of the Steering board, agree to pass the 2013 Operation Plan of the
Steering board. Require Ministries, sectors and localities to review, propose
feasible projects (in development plan, have ability to payback and attract
investors, etc), not later than March 10, 2013, send them to the Ministry of
Planning and Investment for summarizing into List of PPP investment projects,
and submit to the Chief for approval. 3. A few of tasks in next time: - Expeditiously complete the
consolidation of the inter-sector working team on PPP; - Strengthen the proactive, positive
coordination of ministries, sectors which have representatives being members of
the Steering board, aiming to step up implementation of general tasks of the Steering
board as well as tasks on PPP in their fields and sectors. ... ... ... Bạn phải đăng nhập hoặc đăng ký Thành Viên TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN. Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66 - The Ministry of Finance expeditiously
finishes procedures for borrowing EUR 8 million from AFD; the State bank of
Vietnam expeditiously completes announcement on effect of the amounts of USD 20
million borrowed from ADB for the PPP project development support Fund (PDF). - The Ministry of Planning and
Investment shall assume the prime responsibility for, and coordinate with
Ministries, sectors and localities in stepping up training and improving
capability on PPP. - For some specific projects: + Dau Giay – Phan Thiet highway
project: Office of Government consults relevant agencies and submits to the
Prime Minister for consideration and decision. + Bien Hoa – Vung Tau highway
project: Japanese partner has researched in order to carry out by use of PSIF
capital source, hence continue carrying out under this model. + Ninh Binh – Ha Tinh (Bai Vot)
highway project: The Ministry of Transport continues researching in order to
carry out under PPP model and define time, scope of investment for conformity. + Project on upgrading plant of
concentrated sewage treatment in An Nghiep industrial zone, Soc Trang province:
The Ministry of Natural Resources and Environment coordinates with the Ministry
of Planning and Investment and Soc Trang People’s Committee in studying on
capability of loans for project and preferential interest rate from Vietnam
environmental protection Fund. + Project on supply of hospital
logistics: The Ministry of Health establishes a working team, coordinates with
the Ministry of Planning and Investment in order to continue implementation of
contents unified with Hellmann Company. In principle, it must comply with law
of Vietnam. + Project on application of
electronic trade in Governmental procurement: The Ministry of Planning and
Investment expeditiously approves Report on feasible research (FS), dossier of
bidding and organizes selection of investor early in order to put project into
operation. ... ... ... Bạn phải đăng nhập hoặc đăng ký Thành Viên TVPL Pro để sử dụng được đầy đủ các tiện ích gia tăng liên quan đến nội dung TCVN. Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66 Office of Government announces with
the Ministry of Planning and Investment and relevant agencies for
implementation. FOR THE
MINISTER, CHAIRPERSON OF OFFICE
VICE CHAIRPERSON
Pham Van Phuong
Announcement No. 67/TB-VPCP of February 07, 2013, on conclusion of the Deputy Prime Minister Hoang Trung Hai – chief of steering board of investment in the public-private partnership form
Official number:
|
67/TB-VPCP
|
|
Legislation Type:
|
Announcement
|
Organization:
|
The Office of Government
|
|
Signer:
|
Pham Van Phuong
|
Issued Date:
|
07/02/2013
|
|
Effective Date:
|
Premium
|
Gazette dated:
|
Updating
|
|
Gazette number:
|
Updating
|
|
Effect:
|
Premium
|
Announcement No. 67/TB-VPCP of February 07, 2013, on conclusion of the Deputy Prime Minister Hoang Trung Hai – chief of steering board of investment in the public-private partnership form
|
|
|
Address:
|
17 Nguyen Gia Thieu street, Ward Vo Thi Sau, District 3, Ho Chi Minh City, Vietnam.
|
Phone:
|
(+84)28 3930 3279 (06 lines)
|
Email:
|
inf[email protected]
|
|
|
NOTICE
Storage and Use of Customer Information
Dear valued members,
Decree No. 13/2023/NĐ-CP on Personal Data Protection (effective from July 1st 2023) requires us to obtain your consent to the collection, storage and use of personal information provided by members during the process of registration and use of products and services of THƯ VIỆN PHÁP LUẬT.
To continue using our services, please confirm your acceptance of THƯ VIỆN PHÁP LUẬT's storage and use of the information that you have provided and will provided.
Pursuant to Decree No. 13/2023/NĐ-CP, we has updated our Personal Data Protection Regulation and Agreement below.
Sincerely,
I have read and agree to the Personal Data Protection Regulation and Agreement
Continue
|
|